Hi SWAT Users,
I have some confusion regarding the crop scheduling. I have to create crop schedules for different crop. For example, Winter wheat is growing in October in year 1 but harvesting in August in year 2. So My question is, what is
the best way to account for this rotation since winter wheat's planting schedule spans two calendar years. If I use number of rotation year( NROT) is 1 then how SWAT will deal with this ?
Is the Operation shown below is okay?
NROT: 1
October Year 1: Planting of Winter wheat
Year1 : Auto fertilization
Year 1: Auto Irrigation
August Year 2: Harvest and kill of Winter Wheat
or should I do in this way?
NROT: 1
August Year 1 : Harvest and kill of Winter Wheat
October Year 1: Planting of Winter wheat
Year1 : Auto fertilization
Year 1: Auto Irrigation
Management Operations:
1 | NROT: number of years of rotation
Operation Schedule:
10 2 1 28 1800.00000 0.00 0.00000 0.00 0.00 0.00
0.010 11 1 0.75000 0.00 0.00000 0.00 0.00
0.150 10 2 3 91.00000 0.75 63.00000 0.00 1
08 01 5 0.00000
17
Management Operations:
1 | NROT: number of years of rotation
Operation Schedule:
08 01 5 0.00000
10 2 1 28 1800.00000 0.00 0.00000 0.00 0.00 0.00
0.010 11 1 0.75000 0.00 0.00000 0.00 0.00
0.150 10 2 3 91.00000 0.75 63.00000 0.00 1