RE: Cubix dharuheda pics

0 views
Skip to first unread message

Ashish Kaistha

unread,
Aug 24, 2013, 1:21:52 AM8/24/13
to Rakesh Yadav, thecubixproj...@googlegroups.com
Thanks for sharing the photographs...

From: Rakesh Yadav
Sent: ‎23-‎08-‎2013 17:37
To: naruka...@gmail.com; km20...@yahoo.com; Laxman...@gmail.com; ANURAG_...@hotmail.com; atul....@maruti.co.in; ARUN.A...@yahoo.com; saurabh agarwal; Himkar Sharma; rcjai...@gmail.com; Rajesh Jain; lokesh818 .; way...@yahoo.co.in; way....@yahoo.co.in; Arun Sharma; khush...@yahoo.in; amanna....@gmail.com; ankit.mit...@rediffmail.com; kuldeep singh; hawa singh Yadav; Rajesh Biyani; Jatin goel; amitseh...@gmail.com; rajes...@gmail.com; sujeet yadav; khoja....@yahoo.in; bijen...@gmail.com; puna...@yahoo.com; gurpre...@pepsico.com; kk_dub...@yahoo.co.in; kk.dub...@yahoo.co.in; jyoti_...@yahoo.com; atul singh; SURES...@rediffmail.com; Karamvir Dagar; himkar sharma; Ashish Kaistha; PATILSUB...@gmail.com; Sourabh Patil; ANURAG_...@hotmail.com; aditi singh; Shishir Kumar; B_MA...@hotmail.com; ALTA...@rediffmail.com; ALTA...@hotmail.com; Devender Yadav; sheru...@rediffmail.com; kartar singh; sudhir...@yahoo.com; Atul Kumar; weirdo m; subh...@hotmail.com; Shrees...@outlook.com; Rajnish Sharma; Jogender Kumar Sharma; sand....@yahoo.com; anurajs...@gmail.com; carahis...@gmail.com; Sahjad Khan; shyam...@gmail.com; ansh...@gmail.com; rajkum...@gmail.com; aj...@eil.co.in; Ashok Kumar; rakesh...@gmail.com; shivkum...@iffco.in; abhinav singh; Tinku Yadav; Vinod sharma; vikas...@rediffmail.com; drsanjay bhat; Anil Kumar; Anil Kumar
Subject: Fwd: Cubix dharuheda pics



---------- Forwarded message ----------
From: SACHIN soni <sachi...@gmail.com>
Date: Fri, Aug 2, 2013 at 5:13 PM
Subject: Cubix dharuheda pics
To: rakesh...@gmail.com


Find the attachments


kuldeep singh

unread,
Nov 25, 2013, 7:27:38 PM11/25/13
to theCubixProj...@googlegroups.com, Rakesh Yadav
dear friends 
plz tell me abt any update and demand.


On Sat, Aug 24, 2013 at 10:51 AM, Ashish Kaistha <ashish....@gmail.com> wrote:
Thanks for sharing the photographs...

From: Rakesh Yadav
Sent: 23-08-2013 17:37

--
You received this message because you are subscribed to the Google Groups "The Cubix Project Buyer Group" group.
To unsubscribe from this group and stop receiving emails from it, send an email to theCubixProjectBuy...@googlegroups.com.
To post to this group, send email to theCubixProj...@googlegroups.com.
Visit this group at http://groups.google.com/group/theCubixProjectBuyerGroup.
To view this discussion on the web visit https://groups.google.com/d/msgid/theCubixProjectBuyerGroup/52184331.680c440a.5776.ffffc05c%40mx.google.com.
For more options, visit https://groups.google.com/groups/opt_out.

ASHOK KUMAR

unread,
Nov 26, 2013, 12:58:46 AM11/26/13
to thecubixproj...@googlegroups.com
Dear Colleagues,
Despite my request to Mr Neeraj Mishra to ask for 4th Instalment in September,13, these people are not showing any progress wrt site work or updating the clients as to what is the progress in the project work. I booked a flat in A-2 tower and as per Mr Naruks's last mail the instalment is expected in Jan-Feb for A-2 block, then where the work is going on?
Can any body update on these issues.
Thanks & Regards to all.
Ashok


Dr. Ashok Kumar 
Ph: +91 9416994522 (M)   



Date: Tue, 26 Nov 2013 05:57:38 +0530
Subject: Re: [The Cubix Group Update] RE: Cubix dharuheda pics
From: kdp...@gmail.com
To: theCubixProj...@googlegroups.com
CC: rakesh...@gmail.com

km20...@yahoo.com

unread,
Nov 26, 2013, 1:11:08 AM11/26/13
to theCubixProj...@googlegroups.com
It is worthwhile for all of us to ponder and have an action plan as builder agreement gives them ample leeway and skewed for it offers peanuts as penalty for delay

Further their other project is also slow and hence matter on concern it will make sense to meet review

Share your thoughts
Sent from BlackBerry® on Airtel

From: ASHOK KUMAR <agga...@hotmail.com>
Date: Tue, 26 Nov 2013 11:28:46 +0530
Subject: RE: [The Cubix Group Update] RE: Cubix dharuheda pics
To view this discussion on the web visit https://groups.google.com/d/msgid/theCubixProjectBuyerGroup/SNT148-W65AFBA9DDBB367FD940C67BAEC0%40phx.gbl.

Chetan Singh

unread,
Nov 26, 2013, 2:22:05 AM11/26/13
to theCubixProj...@googlegroups.com
Hi All,

Ashok : about the installment its only my personal view not builder's or others..I also have one flat in cubix. I went there in Sept 2013 .i had mentioned in mail,whatever i felt,... I kindly request you please do not target to anyone in group. We are here to share our feelings and i did the same.

I do not know about the issue behind this. I think we should talk to builder about delay.


Thanks
Chetan Singh Naruka




ASHOK KUMAR

unread,
Nov 27, 2013, 1:10:01 AM11/27/13
to thecubixproj...@googlegroups.com
Dear Mr Naruka,
I never targetted anybody including you. Your reference was quoted as you had mentioned that 4th instalment for B tower is expected in Nov-Dec and for A-2 tower it may be Jan-feb or so. It was quite informative to us and you don't have to take it otherwise as I never said that it was builder's view. 
I very clearly wrote that when I asked Mr Neeraj Mishra for my 4th instalment in Sept., I was told that I will get the letter very soon and when will this soon come, I don't know. My opinion if has hurted Mr Naruka, then I regret for it but then if we can't discuss or quote our group members at any place, then group has no meaning and perhaps that's the reason that flat owners are not coming with their express opinions.
Thanks 


Dr. Ashok Kumar 
Ph: +91 9416994522 (M)   



Date: Tue, 26 Nov 2013 12:52:05 +0530

Subject: Re: [The Cubix Group Update] RE: Cubix dharuheda pics

kuldeep singh

unread,
Mar 1, 2014, 2:18:13 AM3/1/14
to theCubixProj...@googlegroups.com

dear friends plz tell me any body is having flat in A-1
and are they get demand
plz tell me.

On Aug 24, 2013 12:32 PM, "Ashish Kaistha" <ashish....@gmail.com> wrote: