Hi 

Under materials in BOM there is a data entry for 'Scrap'. Now i have a query as to whether ERPNEXT is able to generate reports based on the scrap percentage. To make more clearer, there is a paper company that during production  has wastage, so they would for instance like to report the finished goods production against the raw materials used. so basically they would like to track wastage to know how much they have produced.

I hope to hear from you soon.

Thanks 
Joseph 

Umair Sayyed

unread,
Dec 19, 2012, 6:55:39 AM12/19/12
to erpnext-dev...@googlegroups.com
Dear Joseph,

ERPNext doesn't calculate the wastage of raw-material during production process. You will need to make separate Stock Entry to update wastage / scrap after Production entry. The % Scrap in BOM is just for a log.

--
Thanks and Regards,
Umair Sayyed
um...@erpnext.com
www.erpnext.com


Joseph 

--
You received this message because you are subscribed to the Google Groups "ERPNext Developer Forum" group.
To post to this group, send email to erpnext-dev...@googlegroups.com.
To unsubscribe from this group, send email to erpnext-developer...@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msg/erpnext-developer-forum/-/3McT_fyC2gcJ.
For more options, visit https://groups.google.com/groups/opt_out.
 
 





Reply all
Reply to author
Forward
0 new messages