Hi Andre,
Thanks for the reply.
One value of splitting BLI's that are not started is to keep a "cookie
crumble" in that iteration.
It allows us to ask the question during our end-of-iteration
retrospective: "We originally planned to do this task, but for some
reason we didn't even start it. We should keep this in mind so that
we plan better for the next iteration. How can we plan better to avoid
this?"
If we just moved it, we probably would forget that we moved it. I
wonder if what we are doing is indeed correct.
Have you found any documents that talk about how to handle this? I'm
very curious.
-alex-
On Mar 30, 1:12 pm, Andre Nelson <
nel...@fstrf.org> wrote:
> This is a question for which I can see you getting multiple answers.
> I'll give you how we do it at my company (which is a fetus in terms of
> its Agile implementation).
>
> BLI that are not started just get moved either to the Backlog or to the
> next sprint. There is no use splitting them as there was no value even
> remotely added by that BLI so it shouldn't be tracked as part of that
> sprint.
>
> BLI that are partially done. This is a two parter.
>
> 1. For items where some amount of tasks were done, but the item
> cannot be considered complete, we split it and leave it as In
> Progress and Closed
> 2. For items where some amount of tasks were done and this can be