When you split a backlog item, do you close the backlog item in the sprint that you just closed or leave it in open and close it in the next sprint when the item is completed?
Thanks Vijay
Luanne
unread,
Jan 7, 2009, 9:05:35 AM1/7/09
Reply to author
Sign in to reply to author
Forward
Sign in to forward
Delete
You do not have permission to delete messages in this group
Copy link
Report message
Show original message
Either email addresses are anonymous for this group or you need the view member email addresses permission to view the original message
to VersionOne-users
Vijay,
I would recommend closing the story in the sprint you just ended.
With a split you are saying that some of it was completed
and the remaining tasks/tests will carry forward and eventually close
when they are complete.