Not really new to project but custom fields absolutely. For most
projects, I keep it simple with Start, Finish, Hours etc.
What I really need is a field I'm guessing formula that will act as a
traffic stop light depending on how close or over a task is from the
"Finish" field for example.
Ie for green, that would be for tasks 5 days or more away from the
finish date
for yellow, under 5 days from finish
for red, over the finish date
and blue for completed tasks.
--
texmaster
------------------------------------------------------------------------
texmaster's Profile: http://forums.techarena.in/members/142408.htm
View this thread: http://forums.techarena.in/microsoft-project/1256767.htm
Have you looked at the built in Status or Status Indicator field?
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
"texmaster" <texmaste...@DoNotSpam.com> wrote in message
news:texmaste...@DoNotSpam.com...
I think I can provide you with a formula and instructions if you can clarify
this point.
Jonathan
"texmaster" <texmaste...@DoNotSpam.com> wrote in message
news:texmaste...@DoNotSpam.com...
>
For now, I'm comparing it the current date whatever that is when its
opened. My group is new to project and they want the ability to open a
project, look at the current date structure and basically, look for
yellow and pay attention to those tasks.
I'm sorry to say for a group of 8 guys, we have over 35 active projects
and I can't get management to purchase project server this year.
For example,
Many of my projects for now have task name, duration, start finish and
predecessors along with percentage complete and thats it.
I would like to move to what you are proposing having a finish date and
actual finish date to compare when tasks are actually completed.
Sorry if I'm being cryptic.
Thanks for any help you can provide.
'Jonathan Sofer [MVP Wrote:
> ;4645938']What are you using to compare to the finish date? Are you
I'd be curious to know why the built-in status fields Julie mentions are
not sufficient for your need? What's better about the bespoke method
you plan?
--rms
For clarification, it appears as though you want to compare the
Baseline Finish to the current date -- if the Baseline finish is
greater than 5 days away it's green. If the Baseline Finish is less
than 5 days away, yellow, if the Baseline finish is earlier than
today, red, and if the task is finished, blue.
So, to get you started. In a spare text field create the following
formula
IIf([% Complete]=100,"Complete",IIf([Baseline
Finish]=ProjDateValue("NA"),"No Baseline",IIf(DateDiff("d",[Current
Date],[Baseline Finish])>=5,"Green",IIf(DateDiff("d",[Current
Date],[Baseline Finish])>=0,"Yellow","Red"))))
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
"texmaster" <texmaste...@DoNotSpam.com> wrote in message
"JulieS" <Jul...@discussions.microsoft.com> wrote in message
news:OLk62SbS...@TK2MSFTNGP05.phx.gbl...
Jim Aksel, MVP
Check out my blog for more information:
http://www.msprojectblog.com
When I try to put the formula in, it fails claiming Syntax field and
highlights "Current Date"
As far as the graphic indicators, I'm lost there as well.
What goes line by line? for all colors?
Create a custom TASK level TEXT field with the following formula:
IIf([% Complete]=100,"Blue",IIf(ProjDateDiff([Current
Date],[Finish],[Project Calendar])/480<0,"Red",IIf(ProjDateDiff([Current
Date],[Finish],[Project Calendar])/480<5,"Yellow",IIf(ProjDateDiff([Current
Date],[Finish],[Project Calendar])/480>=5,"Green"))))
Set "Calculation for task and group summary rows" to "Formula"
For values to display in Graphical Indicators do the following:
Under Nonsummary rows add 4 values
Test for 'text1' Value(s) Image
contains Blue [set to a blue circle]
contains Green [set to a green circle]
contains Yellow [set to a yellow circle]
contains Red [set to a red circle]
For Summary rows check the box to inherit from nonsummary rows
For Project summary rows check the box to inherit from summary rows
Check the box "Display values in tooltips" (so when you hove the mouse of
the image it shows the text behind it.
Now, if you want to in the formula, you can add more text so instead of just
"Red", you can say "Red, task was due to finish in the past". The key is to
keep the word "Red" in the text because that is what your graphical
indicator looks for (i.e. contains Red)
Hope this helps,
Jonathan Sofer
I didn't see any that actually automatically calculated.
--rms
Did you copy and paste the formula from below? It's possible that
by copying and pasting you've picked up a spare return. Try
copy/paste into note pad first and then edit the formula to remove
any returns.
To your question about the graphic indicators, once you've check
that the formula works -- you're seeing the correct word showing in
the column, right click and choose "Customize field again. Click
the Graphical Indicators button and enter the test, one for each
line.
So, if you've used Text1
Test: equals
Value: Green
Image: Green circle
Next row
Test: equals
Value: Yellow
Image: yellow circle
Each one of the values (Complete, No baseline, Green, Red, Yellow)
should have an image or your can leave the image value blank to show
nothing.
And don't apologize for being "clueless" -- you're far from it :-)
Julie
Project MVP
For some reason every time I try to enter the formula I get a syntax
error and it highlights "current date"
Am I not putting it in the right space? I'm going to "Custom
Attributes" then clicking on "formula"
'Jonathan Sofer [MVP Wrote:
> ;4648777']This should work for you, it works fine on my machine.
Check that you haven't picked up a return in the formula -- there
should be a space but not a return. Click between "current" and
"date" in your pasted formula. Hit delete until the words run
together. Then put a space back in.
Julie
I'm so sorry everyone. I wasn't thinking in the old SQL terminology
about line spacing when cutting and pasting.
My sincerest apologies. Its works perfectly!
Thank you all for your help!!!
:)
Julie