I want task 2 to start no earlier than two weeks after task 1
completes, and I want task 2 to complete no earlier than four weeks
after task 1 completes. I don't want to enter the actual value of ([task
1 complete date]+[2 weeks]) for my start date, because task 1 will have
an end date that is variable.
Can anyone tell me how I could get Project (2007) to accept a formula
for the date restrictions?
Thanks in advance!
--
hayansekki724
------------------------------------------------------------------------
hayansekki724's Profile: http://forums.techarena.in/members/155494.htm
View this thread: http://forums.techarena.in/microsoft-project/1271993.htm
--
Rod Gill
Microsoft MVP for Project
Author of the only book on Project VBA, see:
http://www.projectvbabook.com
"hayansekki724" <hayansekki...@DoNotSpam.com> wrote in message
news:hayansekki...@DoNotSpam.com...
> __________ Information from ESET Smart Security, version of virus
> signature database 4613 (20091116) __________
>
> The message was checked by ESET Smart Security.
>
> http://www.eset.com
>
>
>
__________ Information from ESET Smart Security, version of virus signature database 4613 (20091116) __________
The message was checked by ESET Smart Security.
I'm trying to create a relative time constraint in project, but I can't
seem to find any option other than entering a fixed date. Example
below.
I want task 2 to start no earlier than two weeks after task 1
completes, and I want task 2 to complete no earlier than four weeks
after task 1 completes. I don't want to enter the actual value of ([task
1 complete date]+[2 weeks]) for my start date, because task 1 will have
an end date that is variable.
Can anyone tell me how I could get Project (2007) to accept a formula
for the date restrictions?
Thanks in advance!
--
hayansekki724
------------------------------------------------------------------------
hayansekki724's Profile: http://forums.techarena.in/members/155494.htm
View this thread: http://forums.techarena.in/microsoft-project/1272027.htm
--rms
--
hayansekki724
------------------------------------------------------------------------
hayansekki724's Profile: http://forums.techarena.in/members/155494.htm
View this thread: http://forums.techarena.in/microsoft-project/1272064.htm
There is a concern however. You are requesting a start of task2 "NET."
Ifit starts 3 weeks later is that OK? If it starts later does it still have
to FNET 4 weeks after Task1? Could it finish 10 weeks later? The solution I
have given will only supply one possible scenario. You will have to adjust
the milestone dates lag values to accomplish the result. That you will have
to do on the fly.
Since your task start and ends are somewhat vague, you should also consider
other items that may constrain the duration, work, and cost of Task2.
--
If this post was helpful, please consider rating it.
Jim Aksel, MVP
Check out my blog for more information:
http://www.msprojectblog.com
"hayansekki724" wrote:
> .
>
Note - you should NOT be setting dates for individual tasks. Duration,
links, and resource availability, not management's desires, determine when
tasks are able to take place.
--
Steve House
MS Project Trainer & Consultant
"hayansekki724" <hayansekki...@DoNotSpam.com> wrote in message
news:hayansekki...@DoNotSpam.com...
>
The project owner's specifications determine when the tasks can take
place in this case, so I don't have much option there. :p
Steve House;4694027 Wrote:
> Task 1 is linked to Task 2 with a conventional finish to start
> dependency
> link. Such a link says Task 2 can begin no earlier than the finish of
> Task
> 1.
> Now click the link arrow and add a +2week lag time. NowTask 2 may
> start no
> ealier than 2 weeks after the completion of Task 1. Task 1 get
> delayed,
> Task 2 will too. Set Task 2's duration to 2 weeks. 2 weeks lag plus
> 2
> weeks duration means the expected finish of 2 will be 4 weeks after
> the
> completion of task 1.
>
> Note - you should NOT be setting dates for individual tasks.
> Duration,
> links, and resource availability, not management's desires, determine
> when
> tasks are able to take place.
> --
> Steve House
> MS Project Trainer & Consultant
I may have mistyped. I want task 2 to start no earlier than two weeks
after task 1 and end no later than 4 weeks after task 1. In this case,
task 2 has no duration, it's a delivery deadline for a component of the
project not managed internally, so I'm not concerned with it's actual
duration and start date.
Point taken about using Project to properly schedule tasks. However, in
a case like this where the owner has specified "deliver task 2 between
two and four weeks after Notice to Proceed (task 1)", is my attempt to
force the schedule for this task not correct?
Thanks,
--
hayansekki724
------------------------------------------------------------------------
hayansekki724's Profile: http://forums.techarena.in/members/155494.htm
View this thread: http://forums.techarena.in/microsoft-project/1271993.htm
"hayansekki724" <hayansekki...@DoNotSpam.com> wrote in message
news:hayansekki...@DoNotSpam.com...
>