Can't Delegate Tasks After Upgrading from Project2003 SP2a to SP3

3 views
Skip to first unread message

SJohnson_Aerosim

unread,
Oct 5, 2007, 3:24:00 PM10/5/07
to
Let me preface this by saying we had absolutly no issues with Project server
before upgrading to Project 2003 SP3. Now when a user tries to delegate a
task via Project Web Access the task is not assigned, the send and back
buttons are greyed out and 5 error messages are thrown in the application
event log. The error messages are posted below:

Error 1
Component: PjSvrUtl
File: C:\Office\devsp\project\WebClient\source\server\pjsvrutl\DelegUtil.cpp
Line: 109
Error Number: 0x80040e57
Description: <Description><![CDATA[Assert Detected. The error code was also
included.]]></Description>

Error 2
Component: PjQuery
File:
C:\Office\devsp\project\WebClient\source\server\pjquery\PjGenericQuery.cpp
Line: 1076
Error Number: 0x80040e57
Description: <Description><![CDATA[Assert Detected for Virtual Root
'ProjectServer'. The error code was also included.]]></Description>

Error 3
Component: PjSvrUtl
File: C:\Office\devsp\project\WebClient\source\server\pjsvrutl\DelegUtil.cpp
Line: 171
Error Number: 0x80040e57
Description: <Description><![CDATA[Assert Detected. The error code was also
included.]]></Description>


Error 4
Component: PjSvrUtl
File: C:\Office\devsp\project\WebClient\source\utility\queryutil.cpp
Line: 40
Error Number: 0x80040e57
Description: <Description><![CDATA[Assert Detected. The error code was also
included.]]></Description>

Error 5:
File: C:\Office\devsp\project\WebClient\source\utility\pjadorsutil2.cpp
Line: 318
Error Number: 0x80040e57
Description: <Description><![CDATA[Assert Detected. The error code was also
included.]]></Description>
___________________________________

Component: Microsoft OLE DB Provider for SQL Server
Description: <Description><![CDATA[The conversion of the nvarchar value
'696769686969' overflowed an int column. Maximum integer value
exceeded.]]></Description>

td868

unread,
Oct 12, 2007, 3:31:01 PM10/12/07
to
Did you find a solutons to this problem? I have the same error msg in the
eventlog

SJohnson_Aerosim

unread,
Oct 12, 2007, 3:35:01 PM10/12/07
to

Yes, I paid the 250 bucks to talk to Microsoft. It's a bug in the code and
they are working on a fix which should be in the next 60 days. The only
other option would be for you to restore your DB to a SP2a version and
reinstall project.........No one want's to do that.

----------------------------------------------------------------

jorgeporras

unread,
Oct 22, 2009, 3:48:51 PM10/22/09
to
Hi SJohnsonAerosi

I?m facing the same problem you had two years ago, please let me know whether you found any solution to this. I?ve detected that the MSP_WEB_SP_QRY_AddNewDelegAssns stored procedure is receiving a wrong parameter that overflows an integer value. The current Project Server installation was updated with SP3 a long time ago, since that time we haven?t been able to delegate tasks again.

Please any help will be really appreciated.

SJohnsonAerosi wrote:

Yes, I paid the 250 bucks to talk to Microsoft.

12-oct-07

Yes, I paid the 250 bucks to talk to Microsoft. it is a bug in the code and


they are working on a fix which should be in the next 60 days. The only
other option would be for you to restore your DB t

Previous Posts In This Thread:

On viernes, 05 de octubre de 2007 15:24
SJohnsonAerosi wrote:

Can't Delegate Tasks After Upgrading from Project2003 SP2a to SP3


Let me preface this by saying we had absolutly no issues with Project server
before upgrading to Project 2003 SP3. Now when a user tries to delegate a
task via Project Web Access the task is not ass

On viernes, 12 de octubre de 2007 15:31
td86 wrote:

Did you find a solutons to this problem?
Did you find a solutons to this problem? I have the same error msg in the
eventlog

"SJohnson_Aerosim" wrote:

On viernes, 12 de octubre de 2007 15:35
SJohnsonAerosi wrote:

Yes, I paid the 250 bucks to talk to Microsoft.

Yes, I paid the 250 bucks to talk to Microsoft. it is a bug in the code and


they are working on a fix which should be in the next 60 days. The only
other option would be for you to restore your DB t

EggHeadCafe - Software Developer Portal of Choice
Integrate Membership, Roles and Profile Providers into your ASP.NET 2.0 App
http://www.eggheadcafe.com/tutorials/aspnet/1a040e19-0301-403a-81d2-b4d1a17b879a/integrate-membership-rol.aspx

Jan De Messemaeker

unread,
Oct 22, 2009, 3:53:33 PM10/22/09
to
Hi,

You will havea better chance of getting help in the
microsoft.public.project.server newsgroup
This group essentially handles problems on the desktop product.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
<Jorge Porras> wrote in message news:20091022154...@gmail.com...

0 new messages