Change Tom's working time calendar rther than his Max Units
Max Units don't update the plan they will only show Tom overallocated.
Working time does update the schedule.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Shahriar Nour Khondokar" <ShahriarNo...@discussions.microsoft.com>
wrote in message news:6BE67343-942F-4135...@microsoft.com...
>I am preparing the schedule for a project where multiple resources are
>going
> to work.
> The project has a custom project calendar with a 7-hour working day. This
> calendar was prepared from here:
> Tools > Changing Working Time > Exceptions, Work Weeks > Details.
> Then tasks were created and resources were added.
> But one of the resources, Tom, will not be able to work 7hrs every day for
> the whole duration of the project.
> On certain days he can work 8hrs (this is happening on 2 days, 10/19 and
> 10/20) while on other days he can work 5hrs a day (on 10/26, 10/27).
> To account for this situation, I went to Resource Sheet view, double
> clicked
> Tom to bring up the Resource Information dialog box and from the General
> tab
> entered his Resource Availability as below:
> Available From: 10/12/09 . Available To: 10/18/09 . Units: 100%
> Available From: 10/19/09 . Available To: 10/18/20 . Units: 114% (8/7*100)
> Available From: 10/21/09 . Available To: 10/25/09 . Units: 100%
> Available From: 10/26/09 . Available To: 10/27/09 . Units: 71% (5/7*100)
> Available From: 10/28/09 . Available To: 10/18/10 . Units: 100%
Jim Aksel, MVP
Check out my blog for more information:
http://www.msprojectblog.com
Instead of modifying Tom's max. units, I would just change his
calendar through Tools > Change Working Time and add exceptions to
increase or decrease his hours on the specific days or blocks of
days.
As you note changing max. units and then assigning the resource to
tasks which span the change in max units is not successful as the
assignment is set at the max. units on the first day of the task.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
"Shahriar Nour Khondokar"
<ShahriarNo...@discussions.microsoft.com> wrote in message
news:2E956EBC-E0B8-43B4...@microsoft.com...
>I am preparing the schedule for a project where multiple resources
>are going
> to work.
> The project has a custom project calendar with a 7-hour working
> day. This
> calendar was prepared from here:
> Tools > Changing Working Time > Exceptions, Work Weeks > Details.
> Then tasks were created and resources were added.
> But one of the resources, Tom, will not be able to work 7hrs every
> day for
> the whole duration of the project.
> On certain days he can work 8hrs (this is happening on 2 days,
> 10/19 and
> 10/20) while on other days he can work 5hrs a day (on 10/26,
> 10/27).
> To account for this situation, I went to Resource Sheet view,
> double clicked
> Tom to bring up the Resource Information dialog box and from the
> General tab
> entered his Resource Availability as below:
> Available From: 10/12/09 . Available To: 10/18/09 . Units: 100%
> Available From: 10/19/09 . Available To: 10/18/20 . Units: 114%
> (8/7*100)
> Available From: 10/21/09 . Available To: 10/25/09 . Units: 100%
> Available From: 10/26/09 . Available To: 10/27/09 . Units: 71%
> (5/7*100)
> Available From: 10/28/09 . Available To: 10/18/10 . Units: 100%
Jim Aksel, MVP
Check out my blog for more information:
http://www.msprojectblog.com
"Shahriar Nour Khondokar" <ShahriarNo...@discussions.microsoft.com>
wrote in message news:2E956EBC-E0B8-43B4...@microsoft.com...
See other thread, initiated 15/10/09 16:14 where lots of people replied
to you.
--rms
Unfortunately due to some problems with the MS Servers, not all of
the responses have made it back to the list in the web site.
Julie
"Rob Schneider" <rmschne@yahoo_but_not_often_checked.com> wrote in
message news:eX%233MAUU...@TK2MSFTNGP04.phx.gbl...
> Shahriar,
>
> See other thread, initiated 15/10/09 16:14 where lots of people
> replied to you.
>
> --rms
>
> www.rmschneider.com
<snip>
it looks as though you are having trouble finding your other posts.
See the following page from google groups for all 3 of your
identical posts and the responses.
Read those responses and if you still have questions, please post
your specific questions related to the answers you've been given.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
"Shahriar Nour Khondokar"
<ShahriarNo...@discussions.microsoft.com> wrote in message
news:5B277CB3-5279-4995...@microsoft.com...
>I am preparing the schedule for a project where multiple resources
>are going
> to work.
> The project has a custom project calendar with a 7-hour working
> day. This
> calendar was prepared from here:
> Tools > Changing Working Time > Exceptions, Work Weeks > Details.
> Then tasks were created and resources were added.
> But one of the resources, Tom, will not be able to work 7hrs every
> day for
> the whole duration of the project.
> On certain days he can work 8hrs (this is happening on 2 days,
> 10/19 and
> 10/20) while on other days he can work 5hrs a day (on 10/26,
> 10/27).
> To account for this situation, I went to Resource Sheet view,
> double clicked
> Tom to bring up the Resource Information dialog box and from the
> General tab
> entered his Resource Availability as below:
> Available From: 10/12/09 . Available To: 10/18/09 . Units: 100%
> Available From: 10/19/09 . Available To: 10/18/20 . Units: 114%
> (8/7*100)
> Available From: 10/21/09 . Available To: 10/25/09 . Units: 100%
> Available From: 10/26/09 . Available To: 10/27/09 . Units: 71%
> (5/7*100)
> Available From: 10/28/09 . Available To: 10/18/10 . Units: 100%
it looks as though you are having trouble finding your other posts.
See the following page from google groups for all 3 of your
identical posts and the responses.
Read those responses and if you still have questions, please post
your specific questions related to the answers you've been given.
I hope this helps. Let us know how you get along.
Julie
Project MVP