Define an Enterprize Project Field in Global Template and create
formula to add the cost of all years. This field will be available in
every project. after creating the field close project pro and Open it
again. Then open the project where you have cost data. Try to change
some cost data or proess F9 or Tools -> Calculation and Click Calculate
Now. Now to see your cost click Project -> Project Information Dialog
box. There you will find the value of your Total Cost.
Hope this helps
Regards
Jerry
Just insert or write "Cost" Field to the formula section and save the
field.
Insert "Baseline Cost" If you wanted to see Baseline Cost
Insert "Actual Cost" if you wanted to see Actual Cost
You can use Enterprize Cost or number fields.
Regards
Jerry