For the first, when in the customize field dialogue, have you tried setting
the 'Calculation for task and group summary rows' to 'Rollup', and the
corresponding drop down to 'Sum'. The summary will then show the number of
tasks that meet the criteria of your formula, and your indicators can be '=
0' green and 'greater than 0' Red.
For the second, if you use the above concept, your number field will roll up
and show red if there is only one task in an entire project which is red. If
this is what you want, you can then set the formula for your Enterprise
Project Number field to equal the enterprise task field, and get your RAG
Status for the project to show through in PWA.
--
Hope this Helps!
Ross Andren
http://www.pcubed.com