Thanks --
moe
Most discrepancies that I have seen are caused by:
1) Not setting the baseline
2) Not setting the status date
3) Not sync'ing task progress with resource progress
Does that help? What kind of discrepancies are you observing?
- Andrew Lavinsky
Blog: http://blogs.catapultsystems.com/epm
BCWP is based on one of two measures.. actual work or Physical%complete.
For actual work, you enter your actual work for a task and you earn BCWP
based on that cost estimate. For Physical%Complete it is the % you claim x
Budget at Complete
--