> And how capacity for the sprint is going to calculated?
> Imagine the person is a member of two teams and, say, has 40 hours of
> work per week.
> There are two parallel sprints assigned to these teams. 40 hours have to
> be split somehow between the sprints.
> How? Proportionally? Manually?
> How to track contingents?
Well, you can already assign capacity/hours for a team member. Simply
split it any way you want. I think it is really valid to have people
in multiple teams, especially in small companies where one person can
wear multiple heads. For example, I might mainly work on a the backend
of a product at thus belong to the "backend team", but sometimes the
UI team needs me to do a task for them, so I should be able to get a
few hours for that team in a given sprint.
Contingents are measured in the sprint you mainly work on.
Regards,
Stephan