No.: CMTS/12-237/DMW Allotment/Ph VII+/16-17/136 Dated: 15-05-2017
To
Mr. Ashish Gupta
Circle Head
M/s ZTE India Pvt. Ltd.Jaipur
Sub:-Allotment of DMW under Ph-VII.2 (Lot 2).
In reference to subject mentioned above, kindly find herewith the allotment of DMW for installation and commissioning, supplied by M/s ZTE under Ph-VII.2 (Lot2) on GSM swap/New site of Ph-VII.2 (lot 2) project as below:
|
S. No. |
SSA |
Site ID |
Site Name |
FE Site ID |
FE Site Name |
Type |
Remark |
|
1 |
SWM |
UKR010 |
Karauli 10 |
UKR001 |
Karauli TE |
0.6 |
Supplied by M/s ZTE |
|
2 |
AJM |
UAJ090 |
Abhiyanta Nagar |
UAJ004 |
Vaishali Ngr TE |
0.6 |
Supplied by M/s ZTE |
Note: -
DE (Installation),
CMTS Wing, Jaipur
Copy to:
No.: CMTS/12-237/DMW Allotment/Ph VII+/16-17/140 Dated: 16-05-2017
To
Mr. Ashish Gupta
Circle Head
M/s ZTE India Pvt. Ltd.Jaipur
Sub:-Allotment of DMW under Ph-VII.2 (Lot 2).
In reference to subject mentioned above, kindly find herewith the allotment of DMW for installation and commissioning, supplied by M/s ZTE under Ph-VII.2 (Lot2) on GSM swap/New site of Ph-VII.2 (lot 2) project as below:
|
S. No. |
SSA |
Site ID |
Site Name |
FE Site ID |
FE Site Name |
Type |
Remark |
|
1 |
UDP |
ZUD125 |
Sarada |
CWD001 |
Chawand |
1.2 |
Supplied by M/s ZTE |
Note: -
DE (Installation),
CMTS Wing, Jaipur
Copy to:
No.: CMTS/12-237/DMW Allotment/Ph VII+/16-17/144 Dated: 20-05-2017
To
Mr. Ashish Gupta
Circle Head
M/s ZTE India Pvt. Ltd.Jaipur
Sub:-Allotment of DMW under Ph-VII.2 (Lot 2).
In reference to subject mentioned above, kindly find herewith the allotment of DMW for installation and commissioning, supplied by M/s ZTE under Ph-VII.2 (Lot2) on GSM swap/New site of Ph-VII.2 (lot 2) project as below:
|
S. No. |
SSA |
Site ID |
Site Name |
FE Site ID |
FE Site Name |
Type |
Remark |
|
1 |
JP |
XJP353 |
Balaji IP Site |
XJP352 |
Balaji 002 Existing site |
|
0.6 |
Supplied by M/s ZTE |
|
2 |
CRU |
ZCR146 |
Bhanin |
DRW001 |
Dheerwas Bara TE |
|
1.2 |
Supplied by M/s ZTE |
Note: -
DE (Installation),
CMTS Wing, Jaipur
Copy to: