Greetings all, if I mark a task “complete” in the “All items” view, it updates immediately.  However, if I do it in any other view (e.g. “Today”), the view does not refresh.  I have looked through the properties on the view itself as well as general options, but am not able to find a setting that might be causing this.  I am on version 9.0.78.

 

Cheers

 

Harry

Tom Davis

unread,
Oct 24, 2023, 8:39:05 AM10/24/23
to zoo...@googlegroups.com
I think this may be an issue with .78, so hang on.  I'm prepping a new version now.