Dear All,
Further to QT12 inspection on 7/8/2024, the result of the AIS's inspection as follows:
1) CSLS - PASSED without comments
- The link below is for QT12 documents and draft for submitting letter from MRTC in word file is attached for onward submission to MRTC.
2) IVS2 - FAILED, need to reinspect due to AIS's comments as below.

i. Missing chamber for scour valve and the pipe marker need to rectified.

ii. Need to confirm the tapping valve location. Discrepancies on
the location of pipe marker and sluice valve at site with as-built
plan.


Thank you.
Kind regards, Norshawana for Zaidun-Leeng Sdn Bhd
Dear all,
For info, the email subject already change to CSLS & IVS2.
![]()
Kind regards, Norshawana for Zaidun-Leeng Sdn BhdOn 5/8/2024 8:41 am, Shawana wrote:
Dear all, Please been informed that the QT12 inspection with Pengurusan Air Selangor (AIS) will be conducted as following: CSLS (Jalan Chan Sow Lin) Date : 7th August 2024 (Wednesday) Time : 10.30am IVS2 (Bulatan Kampung Pandan) Date : 7th August 2024 (Wednesday) Time : 12.00pm Thank you.Kind regards, Norshawana for Zaidun-Leeng Sdn Bhd