Dear ZL,
Please provide your time required and fees for preparation of As-builts for CLYS PRV chamber and bulkmeter relocation by filling out the table below.
|
CLYS |
ARE (Days) |
ARE (Fees) |
Drafter (Days) |
Drafter (Fees) |
|
Site Visit |
|
|
|
|
|
ACP Drawings Markup/ Preparation |
|
|
|
|
|
Review/ Checking |
|
|
|
|
|
Respond to ARS |
|
|
|
|
|
Pre-SONO Preparation and Submission |
|
|
|
|
|
Total |
|
|
|
|
Many thanks,
Vincent
Dear ZL,
Can I get your input for this please.
Also, what is the status at site now?
Regards,
Vincent
Dear Vincent,
The time and fees are as below.
The fees is RM13,000
Transportation and other reimbursable Lump Sum RM2,000
Total : RM15,000 Excluding SST.
Thanks
Dear ZL,
Please provide your time required and fees for preparation of As-builts for CLYS PRV chamber and bulkmeter relocation by filling out the table below.
CLYS
ARE (Days)
ARE (Fees)
Drafter (Days)
Drafter (Fees)
--
Site Visit
2
1400
ACP Drawings Markup/ Preparation
4
2800
3
1500
Review/ Checking
3
2100
Respond to ARS
3
2100
Pre-SONO Preparation and Submission
3
2100
2
1000
Total
15
10500
5
2500
Many thanks,
Vincent
You received this message because you are subscribed to the Google Groups "ZLMRT DDC7" group.
To unsubscribe from this group and stop receiving emails from it, send an email to zlmrt-ddc7+...@googlegroups.com.
To view this discussion visit https://groups.google.com/d/msgid/zlmrt-ddc7/SA1PR12MB567034309679D7C6E3EF51BC983F2%40SA1PR12MB5670.namprd12.prod.outlook.com.
Dear Anuar,
MGKT has rejected your proposed fees because it is too high.
Previously, we also did a similar As-Built preparation for BMNS Oil Interceptor relocation (3nos. as-built drawings) and our man-hours are as below, which was approved by MGKT. They have requested for ZL’s time for CLYS to be roughly similar to this BMNS.
Can you review and resend your time please.
|
BMNS |
ARE (Days) |
Drafter (Days) |
|
Site visit |
0.5 |
|
|
ACP Drawings markup/ preparation |
0.5 |
1 |
|
Review/Checking |
1 |
|
|
Respond to ARS |
1 |
|
|
Pre SONO preparation |
1 |
|
|
Total |
4 |
1 |
Many thanks,
Vincent
From: Anuar Aris <an...@zaidun-leeng.com.my>
Sent: Tuesday, December 17, 2024 2:39 PM
To: Chee, Sek Fong Vincent <Vincen...@aecom.com>; sha...@zaidun-leeng.com.my; fauzi...@zaidun-leeng.com.my; zlmrt...@googlegroups.com
Cc: Manuel, Carolina <Carolin...@aecom.com>
Dear Vincent,
Is the scope for BMS Oil Interceptor relocation similar as our
PRV relocation? Apart from as built preparation there are lots of
time spent on resubmission and liaison with authorities including
DBKL and Developer PHB to get approval.
Unless we can submit separate claim for works prior to preparing As Built.
Thanks
Dear Anuar,
Noted on your authority submissions and approval.
The BMNS example I gave below is only for As-built preparation process from ACP, ARS and Pre-SONO. MGKT is looking at roughly the same hours for CLYS As-built preparation.
For Authority submisisions - can you detail the hours for Authority liaison, resubmissions and approvals, etc (separate from your As-built preparation).
Please review the number of hours and try to reduce.
Regards,
Vincent
From: Anuar Aris <an...@zaidun-leeng.com.my>
Sent: Wednesday, December 18, 2024 4:58 PM
To: Chee, Sek Fong Vincent <Vincen...@aecom.com>; sha...@zaidun-leeng.com.my; fauzi...@zaidun-leeng.com.my; zlmrt...@googlegroups.com
Cc: Manuel, Carolina <Carolin...@aecom.com>
Subject: Re: As-built Preparation - CLYS - PRV Chamber and Bulkmeter Relocation
Dear Vincent, Is the scope for BMS Oil Interceptor relocation similar as our PRV relocation? Apart from as built preparation there are lots of time spent on resubmission and liaison with authorities including DBKL and Developer PHB to get approval.
Dear Anuar,
Happy New Year!
Do you have any update on the below please?
Many thanks,
Vincent
Dear Anuar,
I have just received MGKT’s review of your CLYS fees for your further action please.
Many thanks,
Vincent
From: Teoh Soo Keat @ Chang Soo Cheak <SKT...@gamuda.com.my>
Sent: Friday, January 3, 2025 10:10 AM
To: Chee, Sek Fong Vincent <Vincen...@aecom.com>
Cc: Ravichanthiran <Ra...@gamuda.com.my>; Peter Goh Khoon Yaw (UGJV) <pete...@kvmrt-ug.com.my>; Khor Gao Quan <gaoqua...@gamuda.com.my>; Kumaravelan A/L Mayavan (UGJV) <mkumar...@kvmrt-ug.com.my>
Subject: FW: As-built Preparation - CLYS - PRV Chamber and Bulkmeter Relocation
Dear Vincent, Please find our review for ZL’s fee for your consideration. CLYS ARE (Days) ARE (Fees) Drafter (Days) Drafter (Fees) ZL Propose ZL Propose ZL Propose ZL Propose Site Visit 2 1 1400 700 ACP Drawings Markup/ Preparation 4 2
Dear Vincent,
Please find our review for ZL’s fee for your consideration.
|
CLYS |
ARE (Days) |
ARE (Fees) |
Drafter (Days) |
Drafter (Fees) |
||||
|
ZL |
Propose |
ZL |
Propose |
ZL |
Propose |
ZL |
Propose |
|
|
Site Visit |
2 |
1 |
1400 |
700 |
|
|
|
|
|
ACP Drawings Markup/ Preparation |
4 |
2 |
|
2800 |
1400 |
3 |
2 |
1500 |
1000 |
|||
|
Review/ Checking |
3 |
1 |
2100 |
700 |
|
|
|
|
|
Respond to ARS |
3 |
2 |
2100 |
1400 |
|
|
|
|
|
Pre-SONO Preparation and Submission |
3 |
2 |
|
2100 |
1400 |
2 |
2 |
1000 |
1000 |
|||
|
Sub Total |
15 |
8 |
10500 |
5600 |
5 |
4 |
2500 |
2000 |
|
Total |
MYR 7,600 |
|||||||
Regards,
Teoh Soo Keat
Manager - Design & Technical
Design & Technical Department

CONFIDENTIALITY NOTICE:
This email message is for the sole use of the intended recipient (s) and may contain confidential and privileged information. Any unauthorized review, use, disclosure or distribution is strictly prohibited. If you are not the intended recipient, contact the
sender via email reply and destroy all copies of the original message.
from your inbox. If you have any issues, please contact g...@gamuda.com.my.
Disclaimer Note: This e-mail transmission may contain confidential or legally privileged information that is intended only for the individual or entity named in the e-mail address. If you are not the intended recipient, you are hereby notified that any disclosure, copying, distribution, or reliance upon the contents of this e-mail is strictly prohibited. If you have received this e-mail transmission in error, please reply to the sender, so that we can arrange for proper delivery, and then please delete the message from your inbox. If you have any issues, please contact g...@gamuda.com.my.
Dear Vincent,
My counter proposal is as follows:-
Lump sum @ 20% discounted fees of RM13000 x 0.8 = RM10,400
Dear Vincent,
My counter proposal is as follows:-
Lump sum @ 20% discounted fees of RM13000 x 0.8 = RM10,400
Dear Anuar,
As discussed with MGKT, your scope of works should cover all the below. If this can be agreed, we can proceed further.
Please let me know if this is agreeable with you.
Many thanks,
Vincent
From: Anuar Aris <an...@zaidun-leeng.com.my>
Sent: Tuesday, January 7, 2025 4:03 PM
To: Chee, Sek Fong Vincent <Vincen...@aecom.com>; sha...@zaidun-leeng.com.my; fauzi...@zaidun-leeng.com.my; zlmrt...@googlegroups.com
Cc: Manuel, Carolina <Carolin...@aecom.com>
Subject: Re: As-built Preparation - CLYS - PRV Chamber and Bulkmeter Relocation
Dear Vincent, My counter proposal is as follows: - Lump sum @ 20% discounted fees of RM13000 x 0. 8 = RM10,400 Reimbursement for traveling etc : RM 600. 00 Total excl SST: RM11,000. 00 Thank you. Anuar On 18/12/2024 2: 44 PM, Chee, Sek Fong Vincent