In Post:
DATE 1/21/2009
TIME 5:34 PM
LOCATION Wen Library
Topics of Discussion
Patty: Added to google docs a heater and a spill pallet, also emailed
Dr. Anderson about the SEI Grant. Next week: Look at the filtration
stuff on redline. see if Elliot Kennel would be intere. in becoming an
advisor.
Adam: Next week we're doing a demo comparing biodiesel and
petrodiesel. Lady from Homepage says that we can meet in Feb. for a
photo shoot. The date is to be announced (it's either the 18th or
20th). Email Anderson about lab space!?
Kayla: Made a facebook event for this meeting!
Erica: Yay?
Avram: Pigs (spill containment units) from Elliot?
Mandy:Talk to Z about lab space by next week!!!
Proposed Goals for the Following Week
Goals for 09:
Meet with commitee:SEI Grant by end of January
Submit SGA grant by early February- AVRAM!!!!!!!!!!!
Create an advising commitee to help oversee construction: Partially
assembled by
before construction is underway and after we meet with grant
committee.
Potentially pass acount control to someone here more--->
Safety advisor--Elliot Kennel? Check to see if he'll be interested
Process advisor-- Dr. A and/or Dr. Z
Control Engineer---EE dept. or Dr. Z may not even need one.
Secure area for operation: By end of January-we have an area for a
skid, we need a permanent spot though.
Clement Solomon-followup to meet w/unversity official by February
15th.
Equipment ordered: End of February
Basic process built and operable: MAY '09
Testing procedures for sampleing: May '09
SOPs in place by summer of 09'
Controls for system by fall of 09'
FOR NEXT WEEK:
Did DR. A email us back for the grant info?
Avram-SGA grant status, Pig pallets
Mandy- Dr. Z space?
Patty- Filtration, Elliot, Equipment
Adam-Email Dr. Anderson, bring lamps and biodiesel
Dave-BRING LAMPS
Kayla-We <3 the facebook updates, keep them coming
Erica-Do stuff that is important and vital to avoid loosing limbs.
http://wvubiodieselproject.blogspot.com