BWSC street work - WATER, SEWER AND DRAIN REPLACEMENT PROJECT

0 views
Skip to first unread message

37hastings

unread,
Mar 26, 2019, 11:16:16 AM3/26/19
to WestRo...@googlegroups.com, Greener-W...@googlegroups.com

BOSTON WATER AND SEWER COMMISSION
WATER, SEWER AND DRAIN REPLACEMENT PROJECT
WEST ROXBURY

2019 - Ongoing and Upcoming Work
Street                           Limits
➢ Spring Street           Centre St to VFW Pkwy
o April to October (Water/Sewer/Drain)
➢ Partridge Street           Cowing St to Maplewood St
o April to May (Water)
➢ Ledgewood Road           Corey St to Cricket Ln
o April to May (Water)
➢ Gardner Street           #175 Gardner St to End
o May to July (Water)

===

Project Update: Contract 14-308-003
CONTRACTOR: RJV Construction Corp.
CONTRACT NO. 15-309-005
Scope of Work: The work under this contract includes the
replacement of approximately 16,125 linear feet of water
mains, replacement of 2,950 linear feet of sewers and storm
drains and the rehabilitation of 2,340 linear feet of sewers and
storm drains. (Please see back for the map of locations of work)

Work Completed to Date
Street                             Limits
➢ Beech Street          Belgrade Ave to Anawan Ave
➢ Gilmore Terrace          Park St to End
➢ Glenham Avenue          Carrol St to VFW Pkwy
➢ Lyall Street          Brook Farm Rd to VFW Pkwy
➢ Park Terrace          Park St to End
➢ VFW Parkway          Caledonian Ave to Spring St
➢ Brook Farm Road          LaGrange St to Corey St
➢ Ferncroft Road          Corey St to Kirk St
➢ Park Street          March Ave to Robin St

Ongoing and Upcoming Work
Street                Limits
➢ Spring Street           Centre St to VFW Pkwy
o April to October (Water/Sewer/Drain)
➢ Partridge Street           Cowing St to Maplewood St
o April to May (Water)
➢ Ledgewood Road           Corey St to Cricket Ln
o April to May (Water)
➢ Gardner Street           #175 Gardner St to End
o May to July (Water)

CONSTRUCTION IMPACTS
Impacts from the project include water service
interruptions, traffic and parking. Alternate routes are
recommended where feasible. Access to abutters will
be maintained. Baiting for rodent activity is ongoing.

Notices will be mailed when work is scheduled.

The Contractor will have a moving work zone and will
restore parking as the work progresses.

The Contractor will have a moving work zone and will
restore parking as the work progresses.
Customers within the limits maybe required to go on water
bypass. Coordination will be done on an individual basis.
We appreciate the on-going cooperation of the
abutters as we complete these improvements.

Temporary paving will occur as the work progresses.
Permanent paving will occur in 2019 for streets that were
completed in 2018.

Construction Contacts and additional information:
Commission:
Director of Construction: Irene McSweeney (617) 989-7447
Project Engineer: Peter Salvatore (617) 989-7450
Inspector (onsite): Carol Cummings (617) 631-5080
Contractor: RJV Construction Corp.
Superintendent: Victor Pacella (617) 504-0315
Emergency: BWSC Headquarters: (617) 989-7000


---------- Forwarded message ---------
From: Jack Duggan <jack....@boston.gov>
Date: Fri, Mar 22, 2019 at 1:08 PM
Subject: Boston Water and Sewer Commission

I have attached a PDF with information about the upcoming BWSC project in West Roxbury. There are BWSC contacts listed on the first page of the PDF as well as a map of where the work will be happening on the second page.

Jack Duggan
West Roxbury Liaison for
Mayor Martin J. Walsh
Office of Neighborhood Services
617-635-4818

BWSC Construction.pdf