cs605 asnmnt no 4 solution

2 views
Skip to first unread message

kind girl

unread,
Jun 3, 2012, 7:18:35 AM6/3/12
to VU MCS Intellectuals
Take An
Idea
Do Not Copy



Software Engineering-II (CS605)
Assignment # 4
Total marks = 20
Deadline Date = 04-June-2012

Task-1 (Compartmentalization): And
Task-2 (Tasks Allocation):


Task 1:-
1st
task to perform in it is Requirements analysis which involves
following activities:
Communication with system users
Communication with system users to determine specific feature
expectations,
resolution of conflict or ambiguity in requirements as demanded by the
various
users or groups of users, avoidance of feature creep
Documentation
Documentation of all aspects of the project development process from
start to
finish.This task has already done and we got the answers of all of our
questions

Tasks Allocation: This task is allocated to Requirements Engineer Ali
who has
already done his job

Task 2:-
2nd
task to perform in it is System and Software Design and development
which involve
the following activities:-
System design
The system design process partitions the requirements to either
hardware of
software systems. It establishes and overall system architecture.
Task allocation: This task activity is allocated to Architect &
Designer
Asim
Software design
Software design involves fundamental system abstractions and their
relationships.
Task allocation: This task is activity allocated to Architect &
Designer
Raza Developer Ibrahim
System development
System development which involves the development of the software
system
Task allocation: This task is activity allocated to Developer Ibrahim

Software development Take An
Idea
Do Not Copy



Software development involves the development to the entire software.
Task allocation: This task is activity allocated to Developer Waqas
Task 3:-
3rd
task to perform in it is Implementation and Unit Testing which
involve the following
activities:-
Implementation
In Implementation activity software is implemented on the system for
which it is
made .
Task allocation: This task is activity allocated to Developer
Ibrahim.
Unit Testing
Unit Testing Unit testing involves verifying that each unit meets
its specifications.
Task allocation: This task is activity allocated to Developer Waqas

Task 4:-
4th
task to perform in it is Integration and system testing which
involve the following
activities:-
Programs integration
The individual program unit or programs are integrated in it
System testing
Program are tested as a complete system to ensure that the software
requirements
have been met. After testing, the software system is delivered to the
customer.
Tasks Allocation: This task is allocated to Senior Software Tester
Zulfiqar.
Task 5:-
5th
task to perform in it is Operation and Maintenance which involve
the following
activities:-
System installation
The system is installed and put into practical use.
Task allocation: This task is activity allocated to Developer
Ibrahim.
Maintenance
Maintenance involves correcting errors which were not discovered in
earlier
stages of the life-cycle
Task allocation: This task is activity allocated to Developer Waqas

Improving implementation
Improving the implementation of system units and enhancing the
system’s
services as new requirements are discovered
Task allocation: This task is activity allocated to Developer Ibrahim
and
Waqas



Task-3 (Risk Exposure calculation) Take An
Idea
Do Not Copy





As,
Risk probability = 65% = 0.65
Cost per day for a developer =100$
Total cost estimated for 14 days = 14*100=1400$
So,
RE = 0.65 * 1400
RE = 91000$













Ghori*********