DMR dated 01st July'26.

0 views
Skip to first unread message

Facility Manager Address

unread,
Jul 2, 2026, 5:09:36 AMJul 2
to vista CHS ltd_Committee, PM Tech, SILA Reports, vistasociety, Satnam Sethi, Helpdesk Address, Divyashree Shettigar
Dear Members,
 
Greetings of the day!

Kindly find the attached DMR dated  01st July'26.
1. VISTA 1 - P2 LEVEL BMS FAS PANEL'S FAULT CHECKING WORK IS IN PROGRESS BY THE APPOINTED VENDOR (VL ASTRA).
2. VISTA - SOLAR PANEL INVERTER'S PPM DONE BY THE APPOINTED VENDOR (SOLAR SQUARE)
3. VISTA - RAIN WATER BEING DRAINED OUT BY THE HK STAFF.
4. VISTA - TERRACE ALL WATER DRAIN POINTS BEING CLEARED BY THE HK STAFF.
5. VISTA 3 - STAIRCASE WINDOW'S LOUVERS BEING COVERED WITH PLASIC SHEET TO STOP THE RAIN WATER ENTERING THE STAIRCASE, BY THE IN-HOUSE CARPENTER.
6. VISTA 1,2 & 3 - ALL SERVICE AND PASSENGER LIFT PITS CHECKED AND FOUND NO RAIN WATER.

Thanks & Regards,

  

 
Dipesh Patel

Facility Manager-The Address-Vista 1,2 & 3