Dear Members,
 
Greetings of the day!

Kindly find the attached DMR dated 28th May'26.
1. VISTA 3 STILT LEVEL TO P1 LEVEL AREA MONTHLY INSPECTION AND SERVICING OF BOOSTER PUMPS, FIRE SHAFTS AND FIRE EXTIGUISHERS IS IN PROGRESS BY THE APPOINTED VENDOR (VL ASTRA ).
2. VISTA TO MAINGATE CLEANING WORK IN PROGRESS BY HK STAFF.
3. VISTA P1 PARKING AREA NEAR PANORAMA SIDE FLOOR WATER REMOVING WORK IN PROGRESS.

Thanks & Regards,

  

 
Dipesh Patel

Facility Manager-The Address-Vista 1,2 & 3