Kindly find the attached DMR dated  05th July'26.
1. VISTA RAIN WATER DRAINING IN PROGRESS BY HK STAFF.
2. VISTA 21ST TO 1ST FLOOR ALL FIRE SHAFT DOOR AND LOBBY DUSTING IN PROGRESS.
3. VISTA B3 LEVEL NEAR BOREWELL SUMPIT AREA 7.5 HP PUMP CONNECTION DONE BY INHOUSE TECHNICAL TEAM.
Thanks & Regards,

  

 
Dipesh Patel

Facility Manager-The Address-Vista 1,2 & 3