Kindly find the attached DMR dated  04th July'26.
1. VISTA 1 PARTY HALL - ELECTRICIAL CABLING WORK IS IN PROGRESS BY THE APPOINTED VENDOR.
2. VISTA 1,2 &3 AND VISTA GYM'S AIRFRESHNER DISPENSER'S REFILL DONE BY THE APPOINTED VENDOR (SCETMATIC).
3. VISTA - RAIN WATER BEING DRAINED OUT BY THE HK STAFF.
4. VISTA - ALL LIFT PITS OF ALL THETHREE TOWERS CHECKED AND FOUND NO WATER.
5. VISTA - HK CLEANING ACTIVITIES.