Kindly find the attached DMR dated  26th June'26.
1. VISTA 2 GYM ROOM ALL MACHINES BI-MONTHLY SERVICING WORK DONE BY APPOINTED VENDOR.
2. VISTA 1 & 2 FOUNTAIN CIVIL WORK IN PROGRESS BY APPOINTED VENDOR.
3. VISTA STILT LEVEL SWIMMING POOL CHANGING ROOM TILES REMOVING AND CIVIL WORK IN PROGRESS AND VISTA 1 & 2 FOUNTAIN SIDE CEMENT FILL UP WORK IN PROGRESS.
4. VISTA PUMP ROOM FIRE EQUIPMENT EQUIPMENT SERVICING DONE AND FIRE EXTINGUISHER'S CLEANING AND DATE UPDATION DONE BY THE APPOINTED VENDOR.
5. VISTA 1 & 2 FOUNTAIN SIDE NEW TUBELIGHT INSTALLATION WORK DONE.
6. VISTA 1, 2 & 3 ALL FLOORS COBWEB REMOVING IN PROGRESS.
7. VISTA 1, 2 & 3 STILT LEVEL ALL GLASS DOORS CLEANING IN PROGRESS.
Thanks & Regards,

  

 
Dipesh Patel

Facility Manager-The Address-Vista 1,2 & 3
facilityman...@silagroup.co.in
P: +91 7506687809

26.06.2026.xlsm
Reply all
Reply to author
Forward
0 new messages