Fwd: USA Mechanical - Unauthorized Work 5/1 - 219

1 view
Skip to first unread message

Joe Mack

unread,
May 27, 2026, 11:50:50 AM (5 days ago) May 27
to vauxof...@googlegroups.com, The Vaux
We’ll probably need to get RDH advice regarding roof vents. Steve grandfathered in or do we need to change to code

---------- Forwarded message ---------
From: Cynthia H <cjhor...@gmail.com>
Date: Wed, May 27, 2026 at 7:15 AM
Subject: Re: USA Mechanical - Unauthorized Work 5/1 - 219
To: Joe Mack <jmmc...@gmail.com>


Agree. RDH could verify if new code which we may be grandfathered in or if in fact code was not met in 2006.

On Wed, May 27, 2026, 6:51 AM Joe Mack <jmmc...@gmail.com> wrote:
I know. Not sure how to address but now that we know, we will have to discuss how to address it. Maybe RDH

Thanks
Joe
On Tue, May 26, 2026 at 9:28 PM Cynthia Horvath <cjhor...@gmail.com> wrote:
Only Reply to you Joe.

No one on the BMC has the expertise to weigh in.  Perhaps Jerry Jay could.  Curious though, this has gone unnoticed for 20 years. Apparently passed some kind of inspection in 2006.  RDH has done building inspections including the roof and we have a maintenance contract with USA Mechanical. If this was a serious issue, why would it have not been identified before?

Not sure what to think about the Install manual “install K” reference.

Cindy

On May 26, 2026, at 4:20 PM, Joe Mack <jmmc...@gmail.com> wrote:

Well, it just might. I copy Cindy H on this. 
Cindy, can BMC weigh in?
thanks
Joe

On Tue, May 26, 2026 at 3:34 PM Amanda Drake (Vaux Condominium) <va...@kinliving.com> wrote:
Hi Board,

I let USA Mechanical know that you decided against fixing the remaining exhaust vents and they provided me with the following information stating it was installed incorrectly during the original construction of the building. Here is the page of the manual showing the appropriate clearance for them - see section K below. Please let me know if this information changes anything for you all, thanks!



--


 ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌ ‌  Conversation ID: 7e36d9ce-4a65-11f1-a46a-3a599ec4cb98 0acd4ee4-5953-11f1-a2d2-bd282f0b49c0 16faf8fOn Fri, May 8 at 14:13, Paul Block wrote:
I’m generally available most afternoons. On Wednesdays after 130
-p
Sent from my iPhone

On May 8, 2026, at 8:08 AM, Joe Mack <jmmc...@gmail.com> wrote:


I’m up for a planning meeting. I need to be brought back up to speed on all this. 

Re HVAC stuff, are we clear on next steps? Feels klugey (sp?). A planning meeting won’t yield decisions but will set us up to make them

Joe

On Fri, May 8, 2026 at 7:59 AM DIANA DREW-FLEMING <ddrewf...@icloud.com> wrote:
I would like to see a robust discussion about this.  As well as 4th floor HVAC installs. 
 Is it possible to have a planning meeting this week?  I am open every afternoon this coming week.
Tim A seems inclined to agree.  Joe? Paul? Hal? What say you?  (BTW, Paul and I have had elevator meetings at a nearby coffee shop that has quiet space.
Diana

Sent from my iPhone

On May 8, 2026, at 07:51, Paul Block <bloc...@gmail.com> wrote:


If these things are necessary to the health of the building, I want them installed...however we make that happen.  I'd like to see them back on the agenda for a vote.  If the Board votes yes, then we should pay for the work done without authority.  If we vote no, payment should be withheld.
-paul

On Thu, May 7, 2026 at 3:38 PM Amanda Drake (Vaux Condominium) <va...@kinliving.com> wrote:
Hi Board,

It was brought to my attention that while USA Mechanical was on site last Friday to replace the ignitor on water heater #1 and to replace all the exhaust elbows, a member of their team also began work to extend the roof exhaust vents without authorization, and one has been completed. We had requested a quote for that work but never received one.

I spoke with management at USA Mechanical yesterday. They confirmed we will not be charged for the unauthorized work and offered a sincere apology. They have been instructed that we must receive and approve a written quote before any additional work is performed.

Tim Ackely — have you heard back from Kathleen at RDH regarding this matter?

If the Board wishes to proceed with extending the remaining vents, please let me know and we will add the item to the agenda for the May meeting to allow for board discussion and direction.

<s3-8922ac93-aad7-42c8-b6c0-4c23cace6f75-image.png>

Sincerely,

Amanda

--