Attached updated bid for additional 4 unit railings.
Original bid for total repaint of 24 first floor unit railings - $17,000
Updated bid for total repaint of 28 first floor unit railings - $19,833
I believe how he arrived at the cost was $17,000 / 24 = $708.33 * 4 = $2,833.
Total cost then is $40,278 instead of approved $31,500. $40,278 - $31,500 = $8,778 above approved amount.
Cindy
Begin forwarded message:
Subject: District Painting Co. - Proposal for 25-194 - ST - The Vaux - Kin Living [ID2285820-27892]
Date: September 10, 2025 at 11:42:47 AM PDT