Hi Paul,
The *FINAL* contract will not be ready for signature by Wednesday. Attached is the *DRAFT* AIA 104 contract provided by TKE. I am also attaching the specification and supplemental docs that will be attached as exhibits to the contract. We will also want TKE to provide a schedule of values to insert.
I have also not yet received a price from TKE to work on two buildings simultaneously, and we will need that number to put in the contract if the HOA decides they want to do that option.
I also recommend that you have your legal person (Jason Grosz) review the final contract prior to signature.
-
|
|
This email and any files transmitted with it from VDA, Inc. are confidential and intended solely for use of the individual or entity to whom they are addressed. If you received this message in error, please reply to the sender, adding "SENT IN ERROR" to the subject line, then delete this message. Thank you. Before printing, please think about the environment. |
|
----Original Message-----
From: Paul Block <
bloc...@gmail.com>
Sent: Friday, April 10, 2026 4:22 PM
To: Bill Greenland <
wgree...@vdassoc.com>
Cc: Hal Barwood <
wor...@finitearts.com>; Joe McAvoy <
jmmc...@gmail.com>; Diana Drew Fleming <
ddrewf...@icloud.com>; Tim Ackley <
tim.ack...@gmail.com>
Subject: Elevator modernization contract
Bill, will a copy of the intended contract with TKE be available before our meeting on Wednesday?
-paul