Meet to discuss Water valve access in Unit 221, EV Charging Proposal, Mailbox Fix

7 views
Skip to first unread message

Joe Mack

unread,
Oct 22, 2025, 12:00:05 PMOct 22
to vauxof...@googlegroups.com, Cynthia Horvath, Tim Miller (Kin Living)
On Monday, Oct 20, Tim Ackley, Cindy Horvath and I met to discuss the items named in the Subject box of this messag.

Re: Inaccessible water valve in unit 221 and a way to move forward on EV Availability for all in Vaux Garage - we hammered out solutions to move us forward quickly and, I think, satisfactorily to all regarding the Unit 221 Valve Access and EV Charging Strategy. Though I think you will agree, you may not BUT I am pretty confident that we can sell this to you such that we can bring them into the NOV BoD meeting, reach agreement and move forward. Due to the restriction on no more than two BoD members can meet at one time, Cindy and either Tim or I would like to meet with you (Diana, Paul and Hal) individually. (Diana, we will discuss this in French only with you). 

Re mailboxes - Cindy has a proposal to build and install spines in the broken mailboxes (includes one additional spine for inventory just in case for future events), The proposal is for $1050. The solution has been vetted with our mailman. Cindy is working with KIN to get this moving ASAP. Tim and I agreed that the solution works and that we would rather move fast than wait for a BoD meeting to get this done. Bear in mind, that any solution to REPLACE mailboxes will be a MAJOR project with significant disruption due to NEW USPS requirements. Which is to say that Cindy and the BMC have delivered us a BIG WIN here......

thanks
Joe

Paul Block

unread,
Oct 22, 2025, 12:30:53 PMOct 22
to vauxof...@googlegroups.com, Cynthia Horvath, Tim Miller (Kin Living)
Thanks, Joe.
- I am convinced that the unit owner of 221 needs access to the water shut off.  The only question to be resolved is: who pays?...whose financial  responsibility is the work on the drywall?  We need to have a discussion on that aspect of the work.
- Regarding the mailboxes: The repair plan seems appropriate and necessary, and I believe it should move forward ASAP.  I also believe Kin has the authority to order and approve repairs up to $5,000 without Board approval.  If that is the case, and we agree, informally, that it should be done, why don't we just ask Tim M. to move forward?
I'm available to meet at any time.
-paul

--
Officers of The Vaux
---
You received this message because you are subscribed to the Google Groups "vauxofficers" group.
To unsubscribe from this group and stop receiving emails from it, send an email to vauxofficers...@googlegroups.com.
To view this discussion visit https://groups.google.com/d/msgid/vauxofficers/CANX6OJQPuzURcrH9vLu_dYexHNuZbzOBJP2M8oS9%2BVmG69qA1g%40mail.gmail.com.

Joe Mack

unread,
Oct 22, 2025, 12:32:35 PMOct 22
to vauxof...@googlegroups.com, Cynthia Horvath, Tim Miller (Kin Living)

DIANA DREW-FLEMING

unread,
Oct 22, 2025, 2:42:20 PMOct 22
to vauxof...@googlegroups.com
 Bien sûr.   Je suis prêt 
À bientôt 
Diana
Sent from my iPhone

On Oct 22, 2025, at 6:32 PM, Joe Mack <jmmc...@gmail.com> wrote:



DIANA DREW-FLEMING

unread,
Oct 22, 2025, 2:48:11 PMOct 22
to vauxof...@googlegroups.com
Excellent travail,  Cindy.   Félicitations 
d
Sent from my iPhone

On Oct 22, 2025, at 8:42 PM, DIANA DREW-FLEMING <ddrewf...@icloud.com> wrote:

 Bien sûr.   Je suis prêt 

wor...@finitearts.com

unread,
Oct 22, 2025, 8:16:32 PMOct 22
to vauxof...@googlegroups.com

Didn’t we approve this stuff at our last meeting?  — Hal

Joe Mack

unread,
Oct 22, 2025, 8:35:04 PMOct 22
to vauxof...@googlegroups.com
We  approved Kin to survey how many units share 221 issue and to find a fix with wall work. Our idea addresses the ‘who pays’ and specifically addresses Tara’s situation. I think you’ll like it …

EV we did not address. We have developed a solution that just makes infinite sense AND should make most ( including you) happy.

If we can discuss in these pre-Nov meetings, we might be able to bring both in to Nov BOD and get them going asap!

Paul Block

unread,
Oct 22, 2025, 9:00:51 PMOct 22
to vauxof...@googlegroups.com
I'd be happy to meet with one or all of the board members at any time.  
I can meet for beer at McMenamins or coffee at one of the local coffee shops.
Beer late, coffee early.
-paul

Joe Mack

unread,
Oct 22, 2025, 9:09:50 PMOct 22
to vauxof...@googlegroups.com

Tim Ackley

unread,
Oct 22, 2025, 9:17:59 PMOct 22
to vauxof...@googlegroups.com
I thought we approved two motions. 

One to repair unit 221 now, pay for it, and then  determine who is responsible after we identify the root cause of the issue.

A second motion to address the larger issue (number of units), cause, and responsibility.

There was a lot happening. I may not be on target. But resolving the immediate issue quickly and then pursuing a path forward for all units with a similar issue was what I thought was the general direction.

Tim

--
Tim Ackley
2335 NW Raleigh Street Unit 139
Portland, Oregon 97210
 

Joe Mack

unread,
Oct 22, 2025, 9:23:10 PMOct 22
to vauxof...@googlegroups.com
I think you're right. I think that the BMC (esp Michael) has identified a potential fix. 
I think we have come up with a set of protocols to determine who pays for it..... not so?
Joe

Paul Block

unread,
Oct 22, 2025, 9:54:03 PMOct 22
to vauxof...@googlegroups.com
I’m available afternoon up until dinner.  That would be Thursday.
-p

Paul Block

unread,
Oct 23, 2025, 1:11:58 PMOct 23
to vauxof...@googlegroups.com
Yes, so, Joe.  For my part, I will stay consistent with applying the rules and protocols that have dictated who the payer is since the rules were made.
-paul

Reply all