firstly the background stuff.
I've bought a house last December that has two single garages attached
to the left hand side of the house. and the bedroom us on top of the
twin garages.
the house was built in 1985.
One of the previous owners has seen fit to convert the garage nearest
the house into a habitable room and knock through a new opening for a
door from the hall. They also removed the garage door and put in a dwarf
height brick wall and a new DG UPVC window.
In the mean time, the previous owner had free cavity insulation
installed 2 year ago.
So far so good.
Now there is a consumer unit in this now converted garage.
as part of my efforts to update the house, i decided to update the CU
unit and also move itto the hall.
This is because we want to make this room "flexible" accommodation. This
may well include setting up a bedroom from time to time for putting up
ill/dsiabled/elderly relatives. We would like to be able to reset any
tripped RCD/MCB without disturbing the room occupants.
There was no switch isolator in the meter cupboard so I made the
necessary contact with the local electricity board and they've called
round and done the necessary works in order to make it safe for me to
change the CU.
They have put in new 25mm tails from the cutout to the meter and also
from the meter to the new 100A rated switch switch. (the old ones were 16mm)
As the old tails between the switch isolator and the old CU is 16mm,
they have down-rated the original 80A cut out fuse down to 60A and put
brown insulation tape on the cut out to mark this. Clearly the tails
between the switch isolator and the old CU is my responsibility and I am
upgrading this to 25mm and getting the board to come back and put in a
80A or even a 100A fuse.
See the link:
https://www.dropbox.com/s/mdj1fpqbjn07ap7/meter%20cupboard.JPG
Now I have since discovered that the plaster has blown everywhere in the
converted garage. The original "plasterer" has used render and then a
plaster skim.
I started removing the old plaster so that I can get the room
replastered. In doing so, I discovered that the meter tails had been
brought through from the meter cupboard right into the room and surface
mounted on the internal wall. Plastic trunking fitted and then skimmed
over.....
I have also since discovered that the old metal CU is screwed directly
to the breeze block wall and was just plastered around it.
The alarm panel that you see was installed only 5 years ago, which is
below the current CU. The alarm installer was lucky he did not drill
through the meter tails and electrocute himself when fitting the fused
connection unit for the alarm panel, as there is no RCD or earth
protection on these meter tails!
The link is:
https://www.dropbox.com/s/nhmgz5jjsgh1jor/CU%20%26%20alarm.JPG
If some previous house owner had decided to hammer a picture nail into
the wall.... *shudder*
Clearly I am going to rectify this horror.
Now having thought about this, I have three choices regarding the new
meter tails.
1. Chase a channel into the breeze block walls, and then fit a length of
3mm thick 50mm wide steel plate to provide protection
2. use a steel round conduit to place meter tails through and
countersink this into the wall.
3. somehow thread up via the cavity the new meter & earth tails to where
the new CU will be. This is the most difficult option as I'd like to
place the new CU in the hallway. There is also the issue of teh cavity
insulation.
Are options 1 and two acceptable from 17th Ed wiring regs?
Surface mounting the new tails on top of the new plastering in the
converted garage is *NOT* an option due to SWMBO.
Now, I know I need to fit a switch fuse within 3m of the cut out to
protect the meter tails as the new CU would be in the hall, which is
more than 3m away.
I prefer to not have this switch fuse present in the room. the nearest
non-visible location would be next to where the CU is moving to, but
that means the switch fuse is too far away from the cutout.
Now my next question is: Can I put the switch fuse in the meter cupboard
or has it definitely got to be outside the meter cupboard? can the board
disconnect me if they discover this or do they turn a blind eye? the
network in question is Central Networks.
the least attractive alternative would be to put the switchfuse where
the old CU unit is, and then I can run from there to where the new CU is
going. at least the new switch fuse will be much smaller than the old CU.
The alarm panel is being relocated to the loft.
Fortunately for me, all the current T&E from the old CU location goes
past the new proposed CU location so it will be a simple matter to
shortening the cables and so no junction boxes will be needed for
extending cables.
I am aware of my obligations under part p and will get my work inspected
and tested.
All feedback welcome.
Regards,
Stephen