Greetings all,
Herewith an update:
Main power: Joburg City Power
· APK Campus is fed from two independent ring-main circuits. After the initial power-dip, a fault was “flagged” in both circuits. Indicating that there is likely to be a cable fault.
· We do not have the resources in-house to test the cables nor to restore (switch-in) the main 11Kv breakers. A company from Pretoria, Unitest is used for this on a contract basis. Their technician is on site and work is in progress.
· We are hoping that the cables are ok and that it was only the breakers that dis-engaged.
· Time frame: It is anticipated that in the next 1 hour we will know the status/extremity of the problem.
Generator Power
· All the generators are operating, excepting the one supplying power to Core 4, namely C-Lab and parts of D-Lab.
· The thermostat of this particular unit is faulty. It is in the process of being replaced. This particular generator was tested last week and was found to be in order.
· Expected time-frame: Should there be no further problems, this generator should be operational in about 1.5 hours.
Regards,
Eugene
From: O'Brien, Eugene
Sent: 07 August 2017 01:00 PM
To: Academic Development & Support <a...@uj.ac.za>; Baatjes, Jackie <jbaa...@uj.ac.za>; Bentley-Steyn, Lesmarie <lesm...@uj.ac.za>; Champion, Sandra <san...@uj.ac.za>; De Ponte, Lizette <lize...@uj.ac.za>; Geyer, Hoffman <hoff...@uj.ac.za>; Gilbert, Lesley <lagi...@uj.ac.za>; Makinta, Sarah <sar...@uj.ac.za>; Makoti, Pearl <pma...@uj.ac.za>; Mamorare, Nolwazi <nolw...@uj.ac.za>; Matukane, Mzwakhe <mzwa...@uj.ac.za>; Mekgwe, Pinkie <pme...@uj.ac.za>; Nonkwelo, Carol <cnon...@uj.ac.za>; Nxumalo, Zama <znxu...@uj.ac.za>; O'Brien, Eugene <eug...@uj.ac.za>; Qhomane-Goliath, Moipone <moip...@uj.ac.za>; Ramotshela, Mantoa <man...@uj.ac.za>; Ryan, Rory <rr...@uj.ac.za>; Siphoro, Faith <fai...@uj.ac.za>; Tshabalala, Philisile <ptsha...@uj.ac.za>; Wesi, Molehe <mmw...@uj.ac.za>; Xaba, Nonkululeko <prec...@uj.ac.za>; Burger, Kinta <icbu...@uj.ac.za>; Gravett, Sarah <sgra...@uj.ac.za>; Mamorare, Nolwazi <nolw...@uj.ac.za>; Marwala, Tshilidzi <tmar...@uj.ac.za>; Mketi, Keitumetse <kcm...@uj.ac.za>; O'Brien, Eugene <eug...@uj.ac.za>; OBrien, Patrick <pob...@uj.ac.za>; Parekh, Angina <apa...@uj.ac.za>; Rensburg, Ihron <ilren...@uj.ac.za>; Broadbent, Alexander <abbro...@uj.ac.za>; Engels, Marietjie <men...@uj.ac.za>; Freschi, Federico <ffre...@uj.ac.za>; Gravett, Sarah <sgra...@uj.ac.za>; Hadjiapostolou, Barbara <bar...@uj.ac.za>; Layte, Daizeline <dla...@uj.ac.za>; Louw, (Ina) <in...@uj.ac.za>; Meyer, Debra <dme...@uj.ac.za>; Moyo, Gugulethu <gu...@uj.ac.za>; Mpedi, Letlhokwa <lgm...@uj.ac.za>; Nkhumane, Paballo <pnkh...@uj.ac.za>; Singh, Lorna <lsi...@uj.ac.za>; Sinha, Saurabh <ssi...@uj.ac.za>; Swart, Andre <and...@uj.ac.za>; Theunissen, Breggie <breg...@uj.ac.za>; Van Lill, Daneel <dane...@uj.ac.za>
Cc: Manyaka, Joe <jman...@uj.ac.za>; Van der Watt, Andre <andr...@uj.ac.za>
Subject: Power Failure
Greetings Colleagues,
We experienced a power dip at both APB and APK campuses, approximately 20 min ago.
The power has been restored at APB, however not at APK. On APK we running on generator power.
If you experiencing any specific power issues, please contact us directly:
Eugene: 082 494 3711
Andre vd Watt: 083 632 3443
Dr Joe Manyaka: 074 184 5738
Kind regards
Eugene
Eugene O’ BrienExecutive Director: Operations
Auckland Park CampusCorner Kingsway and University Roads
Tel Office: +27 11 559 4991Tel Mobile: +27 82 494 3711