A revised Natcar calendar is at http://bit.ly/5frn4C. It contemplates
getting back on schedule by April 15.
We need to get into recovery mode right away. I believe that we can
compress the development time a little bit by moving the "Car
Assembled" date to March 9.
MARCH 9: CAR ASSEMBLED
That means that parts must be ordered by Feb 26. That means that
circuit boards must be laid out by Feb 23.
EE184D students, be sure that your formal project plans are sync'd
with the Revised Natcar Calendar.
If you have trouble getting access to the calendars, please let me
know.
Mike