 Terlampir Dokumen Sebagai Berikut :

1. UBS2B-A-0-80-PE-0001  : Correspondence Procedure Rev. 3
2. UBS2B-A-0-80-PE-0002  : Document Preparation ProcedureE Rev. 3
3. UBS2B-A-0-80-PE-0004  : Review & Approval Procedure  Rev. 3
4. UBS2B-A-0-80-PE-0005  : Invoicing Procedure (EPC CONTRACT)Rev. 3
5. UBS2B-A-0-80-PE-0006  : Progress Measuremet Prosedure Rev. 1
6. UBS2B-A-0-10-GA-0008  : Overall General Layout Rev. 0
7. UBS2B-A-0-10-GA-0009  : General Layout Plan (UBS-IIB To QSL-1   
                                           UBS-III/IV) Rev. 0
8. UBS2B-A-0-10-GA-0010  : General Layout Plan (UBS-III/IV To UBS-IIB) Rev. 0

Kami kirimkan dengan Transmittal No. UBS2B-T-AJ/PP-0019

Demikian disampaikan agar segera mendapat persetujuan.
atas perhatian dan kerjasamanya kami ucapkan terima kasih.


salam,



Abdullah Fanani
Project Manager
Transmittal 19.jpg
1. document coresspondence _pusri_rev.3 submit.pdf
2. Document Preparation Procedur rev.3 Submit.pdf
4. Review & Approval Procedure Rev.3.pdf
5. Invoicing Procedure (Contract EPC).pdf
6. Progress Measurement Procedure.pdf
UBS2B-A-0-10-GA-0008.pdf
UBS2B-A-0-10-GA-0009.pdf
UBS2B-A-0-10-GA-0010.pdf