On 2016-08-13 11:06, Cédric Krier wrote:
> On 2016-08-13 10:12, Cédric Krier wrote:
> > On 2016-08-07 23:33, Cédric Krier wrote:
> > > Hi,
> > >
> > > The coming weekend, we will take benefit of the contract renewal of the
> > > main server to migrate to a new one (more powerful for almost the same
> > > price).
> > > The process will require to stop the current server to copy all the data
> > > to the new one. This will bring down almost all our services on
> > > *.
tryton.org. The transfer is expected to take about 4 hours so it is
> > > planned to do it this Saturday August 13th at 9:00 CEST.
> > >
> > > We will keep you informed on this mailing list during each steps.
> >
> > The server is bringing down to start the transfer.
>
> The migration is delayed because it is not possible to reboot the server
> in the rescue mode to perform the transfer. A ticket has been created at
> OVH. If we do not get a solution soon, I will restart the server and
> postpone the migration.
The process can be continued. The mother board of the server needed to