On 2017-03-20 07:31, 'Artem Braga' via tryton wrote:
> понедельник, 20 марта 2017 г., 1:25:05 UTC+2 пользователь Cédric Krier
> написал:
> >
> > On 2017-03-19 11:58, 'Artem Braga' via tryton wrote:
> > > Is it possible to get some use case where supply period at Production
> > > Configuration could be used? I've read module documentation
> > > here:
> >
http://doc.tryton.org/4.2/modules/stock_supply_production/doc/index.html
> > > but the meaning of Supply Period is not so clear for me though.
> >
> > You need to produce in advance because production takes times. And also
> > you may need to make production in cascade. So the system can not know
> > until which date in the future does it need to look to see what needs to
> > be produced. The period allow to define from now up to which date it
> > will look the stock levels.
> >
>
> Thanks for this detailed explanation. Regarding stock levels you mention
> here- do you mean stock levels of finished goods?
In Tryton, there is no such concept as "finished goods". There are only
another location etc. So every goods in every storage location are being