Subodh Thanks for update, But as you said if ashiyana will deliverd the project by 2018 then why they are raising demand
in such a short duration. Is demand made correct as per schedule and plan communicated us.. has anyone visited the site recently??
--------------------------------------------
On Tue, 14/10/14, subodh patil <patilsub...@gmail.com> wrote:
Subject: Re: CuBix Status Update
To: "lokesh garg" <lokes...@hotmail.com>
Cc: "Chetan Singh" <naruka...@gmail.com>, "shyam...@gmail.com" <shyam...@gmail.com>, "bijen...@gmail.com" <bijen...@gmail.com>, "subh...@hotmail.com" <subh...@hotmail.com>, "amitseh...@gmail.com" <amitseh...@gmail.com>, "sheru...@rediffmail.com" <sheru...@rediffmail.com>, "km20...@yahoo.com" <km20...@yahoo.com>, "puna...@yahoo.com" <puna...@yahoo.com>, "kdp...@gmail.com" <kdp...@gmail.com>, "amanna....@gmail.com" <amanna....@gmail.com>, "rcjai...@gmail.com" <rcjai...@gmail.com>, "ksyad...@gmail.com" <ksyad...@gmail.com>, "sujee...@gmail.com" <sujee...@gmail.com>, "Himkar...@ranbaxy.com" <himkar...@ranbaxy.com>, "kk.dub...@yahoo.co.in" <kk.dub...@yahoo.co.in>, "SURES...@rediffmail.com" <sures...@rediffmail.com>, "krishna dubey" <kk_dub...@yahoo.co.in>, "sand....@yahoo.com" <sand....@yahoo.com>, "rajes...@gmail.com" <rajes...@gmail.com>,
"dba.ami...@gmail.com" <dba.ami...@gmail.com>, "sagarw...@gmail.com" <sagarw...@gmail.com>, "atul...@gmail.com" <atul...@gmail.com>, "shivkum...@iffco.in" <shivkum...@iffco.in>, "carahis...@gmail.com" <carahis...@gmail.com>, "way...@yahoo.co.in" <way...@yahoo.co.in>, "jyoti_...@yahoo.com" <jyoti_...@yahoo.com>, "anurajs...@gmail.com" <anurajs...@gmail.com>, "PPRAMO...@rediffmail.com" <ppramo...@rediffmail.com>, "aj...@eil.co.in" <aj...@eil.co.in>, "jogend...@gmail.com" <jogend...@gmail.com>, "B_MA...@hotmail.com" <b_ma...@hotmail.com>, "ansh...@gmail.com" <ansh...@gmail.com>, "ALTA...@hotmail.com" <alta...@hotmail.com>, "HIMKAR...@gmail.com" <himkar...@gmail.com>, "way....@yahoo.co.in" <way....@yahoo.co.in>, "ankit.mit...@rediffmail.com" <ankit.mit...@rediffmail.com>, "agga...@hotmail.com" <agga...@hotmail.com>, "hawasi...@gmail.com"
<hawasi...@gmail.com>, "KARAMVIR...@gmail.com" <karamvir...@gmail.com>, "gurpre...@pepsico.com" <gurpre...@pepsico.com>, "PATIL....@gmail.com" <patil....@gmail.com>, "Atul....@maruti.co.in" <atul....@maruti.co.in>, "khush...@yahoo.in" <khush...@yahoo.in>, "yada...@gmail.com" <yada...@gmail.com>, "sudhir...@yahoo.com" <sudhir...@yahoo.com>, "khoja....@yahoo.in" <khoja....@yahoo.in>, "arun.a...@yahoo.com" <arun.a...@yahoo.com>, "akum...@eicherpolaris.in" <akum...@eicherpolaris.in>, "jating...@gmail.com" <jating...@gmail.com>, "sahja...@gmail.com" <sahja...@gmail.com>, "rajesh....@gmail.com" <rajesh....@gmail.com>, "ALTA...@rediffmail.com" <alta...@rediffmail.com>, "kalkaes...@gmail.com" <kalkaes...@gmail.com>, "rakesh...@gmail.com" <rakesh...@gmail.com>, "rajkum...@gmail.com" <rajkum...@gmail.com>, "akuma...@gmail.com" <akuma...@gmail.com>,
"LT.ADI...@gmail.com" <lt.adi...@gmail.com>, "DYADA...@gmail.com" <dyada...@gmail.com>, "SHISHI...@gmail.com" <shishi...@gmail.com>, "drsanja...@gmail.com" <drsanja...@gmail.com>, "atu...@gmail.com" <atu...@gmail.com>, "rajat...@yahoo.com" <rajat...@yahoo.com>, "vikas...@rediffmail.com" <vikas...@rediffmail.com>, "ASHISH....@gmail.com" <ashish....@gmail.com>, "rcjai...@gmail.com" <rcjai...@gmail.com>, "abhinav...@gmail.com" <abhinav...@gmail.com>, "rajnish...@gmail.com" <rajnish...@gmail.com>, "Shrees...@outlook.com" <shrees...@outlook.com>, "ANURAG_...@hotmail.com" <anurag_...@hotmail.com>, "Nitin Bansal" <bansal...@gmail.com>
Date: Tuesday, 14 October, 2014, 10:38 AM
I got a
call from Ashiana for the demand and they are promising
possession by 2017 so its understood not before 2018,
moreover the flat build by dwarkadhis are yet to be sold
and there is no water supply over there so 2017 would be a
optimistic view.
On Mon, Oct 13, 2014 at
8:48 PM, lokesh garg <lokes...@hotmail.com>
wrote:
Demand received.. But has any one met with the
management.. Wanted to check what is the update on delivery
schedule
On 13 Oct 2014 16:23, Chetan Singh <naruka...@gmail.com>
wrote:
I have received 4th demand for Tower B and
20/10/2014 is due date.
On Sun, Oct 12, 2014 at 12:01 PM, krishna dubey
<kk_dub...@yahoo.co.in>
wrote:
Hi All,
Good Morning, I received demand of 7th Installment for Tower
A. 6th Floor Roof slab completed,
Could anyone update recent project status at site if any of
you might visited at Cubix. You guys also received demand
for the same ?
Best Regards
Krishna Kant Dubey