FW: Sir, i acknowledge receipt with thanks Re: TANGEDCO COLLECTION OF O&M CHARGES ORDER ISSUED

1,381 views
Skip to first unread message

raja

unread,
Jul 18, 2011, 1:04:24 AM7/18/11
to teca...@googlegroups.com, te...@airtelmail.in, finance

 

 

From: christopher christopher [mailto:chris...@nagamills.com]
Sent: Saturday, July 16, 2011 5:53 PM
To: chiefadvisor tasma
Cc: IWPA - HEAD QUARTERS; iwpa hq; iwp...@windpro.org; "chairman.iwpa"; te...@airtelmail.in; sima; simacbe; cii.ta...@cii.in; indian wind; VELATAL SPINNING MILLS PVT LTD; Manmathan N.; premier mill - Jayachandran; raja
Subject: Sir, i acknowledge receipt with thanks Re: TANGEDCO COLLECTION OF O&M CHARGES ORDER ISSUED

 

To, The Chief Advisor,

Sir,

i acknowledge receipt of your prompt and clear replies with thanks and

regards
s christopher muthiah

On Sat, Jul 16, 2011 at 4:19 PM, chiefadvisor tasma <chiefa...@tasma.in> wrote:

Dear Mr.Christopher,

 

Please find below my responses.

 


Error! Filename not specified.

 

 

Regards,


Dr.K.Venkatachalam,
Chief Advisor,
Tamilnadu Spinning Mills Association,
#2, Karur Road, (Near Beschi College),

Modern Nagar, Dindigul - 624 001.
India
Phone:  +91 451 6454666, 6454667, 6454668
Fax :     +91 451 2433637
Mobile:  +91 98421 33318
            +91 94433 69858
URL: www.tasma.in

----------------------------------------------

On Sat, Jul 16, 2011 at 4:08 PM, christopher christopher <chris...@nagamills.com> wrote:


To,
The IWPA/All concerned,

dear sirs,

1) The TANGEDCO  has made a circular that all windmills irrespective of date of  commissioning are liable to pay with effect  from  01/06/2011  @ Rs 1.60 lacs per year per MW  if they are connected through the TNEB SS  to the Grid .

 Forwarding the copy of the circular for info and needful.

     The TANGEDCO proceedings are unilateral and arbitrary. It was issued without the approval of TNERC and therefore, it cannot sustain on its own. Windmill consumers have to make a challenge. TASMA is already planned to file a MP before TNERC.   


2) Higher slot to lower slot adjustment still not allowed . In fact the TNEB, Dindigul EDC has started billing in 5 slot wise (C1, C2, C3, C4, C5) rather than the earlier 3 slotwise (Peak (C1+C2), Night (C5) , others (C3+C4).  Although the APTEL dismissed the TNEB appeal and there were assurances  that the circulars allowing the higher slot to lower slot adjustments will be permitted still no circular has been issued.

    A member of TASMA has already approached High Court and the matter is likely to be decided shortly.  


3) The Wheeling charges are payable only for the windmill units adjusted during the month.  whereas the TNEB in DIndigul EDC is deducting the 5% wheeling charges  on the gross generation.  This is also against the TNERC orders.

    A DRP has to be filed by the individual captive consumer at TNERC and then only, justice could be maintained.  



forwarded for kind consideration and any needful.

 with kind regards
--
S.Christopher Muthiah,
Naga Limited, No.1,Tiruchy Road, Dindigul-624 005, Tamil Nadu, South India.
09944990090;chris...@nagamills.com;chris...@rediffmail.com






--
S.Christopher Muthiah,
Naga Limited, No.1,Tiruchy Road, Dindigul-624 005, Tamil Nadu, South India.