Ref,
202509004 | Peradeniya_EFac_Temp_TM0099-Event Upgrade | AP_2025_2067 | Manjula | Central |
202509004-1 | Peradeniya_EFac_Temp_TM0099-Event Degrade | AP_2025_2067 | Manjula | Central |
202509004-2 | Peradeniya_EFac_Temp_TM0099-Event Upgrade-Material Supply | AP_2025_2067 | Manjula | Central |



Commissioning Data Details :
Temporary Site.
Can operate from Integration License

Detailed Project Scope(AP Upgrades) :
Scope
New Temporary site with 5G for Peradeniya Eng Faculty exhibition
Target On Air Date = 22nd September
Backhaul and Power
Power and OFN connectivity needs to be extended from existing Lamp pole [Lamp pole will be shutdown during temp site operation]
path distance from Lamp to new Cabinet Aprox 40m
Both cables should be laid underground [trench] as per University administration
After event power and fiber needs to be reverted back to Lamp Pole
Tree Site TE installation
Place a new Outdoor cabinet near Mobitel Tree and install 2 Nos of BB cards and other equipment [1 BB for DCS/4G and other for 5G NR]
Install 5 Nos of antennas for each of 3 sectors as per below provided Table
2 Nos of 5G antennas and 5G RRUs to be taken from Kotugodella_St [Removed items during perahera already available in site cabin]
Connect RRUs to relevent antennas and configure RET connections
L26 RRU8863 needs to be shared between Sec2 and sec3
Connect 2 Nos of 5G RRUs to one BB card
Connect all other 8 Nos of RRUs to be connected to other BB card
Install a GPS and share clock between BB cards
Commission the site
Antenna Details


Required Materials (AP Upgrades) :
Required
18 Port Antennas - 2 Nos
Dual Array Antenna - 1 Nos
2Split 4T4R Antennas - 2 nos
BB6630 Units - 1 Nos
RRUS12B3 (For DCS) - 2 Nos
RRU4499 or RRU4443 - 5 Nos
RRU8863 - 1 Nos
RRU8863n78 [For 5G NR] - 2 Nos (To be taken from Kotugodella_St Cabin)
Ericsson SFP Normal - 16 Nos
Ericsson high speed SFP (for 5G) - 4 Nos
Ericsson RRU CPRI fiber cables 70m - 10 Nos
Ericsson RRU DC power cables - 350m
Ericsson RRU Power connectors - 10 Nos
RRU8863 to 18 Port Jumpers 5m - 8 Nos
RRU4499 or RRU4443 to Dual Array ant jumpers 1m - 4 Nos
RRU4499 or RRU4443 to 2Split ant jumpers 1m - 16 Nos
RRUS12B2 to 18 Port Jumpers - 4 Nos
RRU8863n78 to 18 Port Ant Cluster cables 1m - 2 Nos
Ericsson GPS Kit - 1 Nos




|
|

From: not...@dialog.workhub24.com <not...@dialog.workhub24.com>
Sent: Tuesday, September 23, 2025 7:05 AM
To: oxcentur...@gmail.com; oxcenture....@gmail.com
Subject: INH_Central_TM0099_Peradeniya_EFac_Temp_AP Upgrades_New Site Installation_AP_2025_2067_Event - New Site - Task Acceptance
|
| Peradeniya_EFac_Temp_TM0099-Event Upgrade-Contract | AP_2025_2067 | 202509004 |
| Peradeniya_EFac_Temp_TM0099-Event Degrade-Contract | AP_2025_2067 | 202509004-1 |
| Peradeniya_EFac_Temp_TM0099-Event Upgrade-Non Contract | AP_2025_2067 | 202509004-2 |