Opposite of a vacation?

55 views
Skip to first unread message

John Carlyle-Clarke

unread,
Apr 19, 2013, 9:39:54 AM4/19/13
to taskjugg...@googlegroups.com
Hi-

How can I add to the plan the fact that a resource is intending to work 1 day on a specific weekend in order to do some work that can only be done at a weekend? I can't see any simple way to achieve this. Am I missing one?

John

Bas de Bruijn

unread,
Apr 19, 2013, 10:20:26 AM4/19/13
to taskjugg...@googlegroups.com
--
You received this message because you are subscribed to the "TaskJuggler Users" group.
To post to this group, send email to taskjugg...@googlegroups.com
To unsubscribe from this group, send email to
taskjuggler-us...@googlegroups.com
For more information about TaskJuggler visit http://www.taskjuggler.org
---
You received this message because you are subscribed to the Google Groups "TaskJuggler Users" group.
To unsubscribe from this group and stop receiving emails from it, send an email to taskjuggler-us...@googlegroups.com.
For more options, visit https://groups.google.com/groups/opt_out.
 
 

John Carlyle-Clarke

unread,
Apr 19, 2013, 10:30:24 AM4/19/13
to taskjugg...@googlegroups.com
That is absolutely perfect! Many, many thanks Bas.


You received this message because you are subscribed to a topic in the Google Groups "TaskJuggler Users" group.
To unsubscribe from this topic, visit https://groups.google.com/d/topic/taskjuggler-users/wKCau4H00Xo/unsubscribe?hl=en-US.
To unsubscribe from this group and all its topics, send an email to taskjuggler-us...@googlegroups.com.

For more options, visit https://groups.google.com/groups/opt_out.
 
 



--
John Carlyle-Clarke
Technical Director
Fastmarkets Ltd


Ground Floor Office Suite, London Road Office Park
Salisbury, Wiltshire, SP1 3HP, UK

Telephone: +44 (0) 1722 424 383
Direct Dial: +44 (0) 1722 439 408


Reply all
Reply to author
Forward
0 new messages