Hello Dave,
Thank you very much. That's exactly what I was afraid of.
As I said, my possible scenario is as follows:
I have a task with a duration of 5 days and 6 hours, and I assign 2 resources to it. Resource A has a standard time of 8 hours and Resource B has 9 hours.
The calculation of hours would be 46 hours for resource A and 51 hours for resource B. so I'll have an issue here
Thanks anyway.