One possible solution to fix this "occasional" - in the case you are using bookings to track actual progress, and bookings may work on any day and any time, just specify {overtime 1/2}:
https://taskjuggler.org/tj3/manual/overtime.booking.html
If this is just per person that occasionally work more than
planned.
However if you are planning some period of more/extra work then you can list shifts:
https://taskjuggler.org/tj3/manual/shifts.resource.html
and declare these "periods" with a proper name why are you doing it .. it may also keep project plan nicer to read afterwards.
BR Uros
--
You received this message because you are subscribed to the "TaskJuggler Users" group.
To post to this group, send email to taskjugg...@googlegroups.com
To unsubscribe from this group, send email to
taskjuggler-us...@googlegroups.com
For more information about TaskJuggler visit http://www.taskjuggler.org
---
You received this message because you are subscribed to the Google Groups "TaskJuggler Users" group.
To unsubscribe from this group and stop receiving emails from it, send an email to taskjuggler-us...@googlegroups.com.
To view this discussion on the web visit https://groups.google.com/d/msgid/taskjuggler-users/6b23c4d4-7fea-b4ca-1979-05f5c655cc85%40isotel.eu.
-- Jakob Schöttl Phone: 0176 45762916 E-mail: jsch...@gmail.com PGP-key: 0x25055C7F
In my case they are added automatically under tasks, ... more
details:
For my project management I created a python script that fetches
from svn (irreversible proof of work) excel sheets from all
collaborators and imports their "progress report" lines as
bookings inserted into the project files themselves, via a unique
reference which is in our case a ticketing system (open source
trac, but any ticketing system could be used as gitlab, jira,
...); before I used aux files to supplement this information;
That's how I control actual plan which is then also the actual
P&L used to do progress reports, critical path analysis,
invoicing, ..
why I decided so:
I am missing some better connection with the ticketing system to handle (warn) closed tickets there and here, ... and priority management, which are declared specifically in the trac (severity vs. priority matrix) ...