repeated task - is it possible to specify it?

63 views
Skip to first unread message

Ram C

unread,
Apr 28, 2013, 2:34:02 AM4/28/13
to TaskJuggler Users
If I need to have a set of tasks (or just one task) repeated N times,
each one kicked off with a delay - is there as way to specify it? From
what I can tell, the tasks (be they 3, or 4, or N) need to be
explicitly specified - essentially hard coded. Is that right?

Chris Schlaeger

unread,
Jun 23, 2013, 7:31:21 AM6/23/13
to taskjugg...@googlegroups.com
Yes, but you could use parameterized macros to simplify the typing.

In case the repeat is weekly and you don't need dependencies on the segments you can use shifts.

Chris 