I manually changed the extension to .tji and tried to run TJ3 on the
file with the includes and I get an error saying that there is an
unexpected 'project' token:
Error: Unexpected token 'project' found. Expecting one of :eof
I've tried placing the include statement in different places on the
main project file and I still get the same error.
Should I just use timesheets?
--
RAV
I can't see how the -booking file could end up with a .tjp extension.
Can you please provide an example project and the exact command line
you use to run tj3?
Thanks,
Chris
I run TJ3 on this file, without altering it:
tj3 --freeze template.tjp
This produces a template-bookings.tjp file.
When I made my original post, I was trying to get acquainted with the
new version, playing with the template to test out the tracking. I couldn't
get it to work but I kept working on my project for planning purposes.
Today, I tried the --freeze on my project file and it worked with no
issues and the imports also worked. Maybe it's something about the
template?
About timesheets, do they provide a way to enter the bookings? I very
interested in the status reporting in the timesheets.
--
RAV
> --
> You received this message because you are subscribed to the "TaskJuggler Users" group.
> To post to this group, send email to taskjugg...@googlegroups.com
> To unsubscribe from this group, send email to
> taskjuggler-us...@googlegroups.com
> For more information about TaskJuggler visit http://www.taskjuggler.org
Ok, found it. There was an error ("no trackingscenario defined") but
tj3 did not abort properly. I've fixed that now. If you want to use
--freeze, you need to tell TJ which scenario should be used for
tracking the actual progress.
I've fixed tj3 now to properly abort on this condition.
> About timesheets, do they provide a way to enter the bookings? I very
> interested in the status reporting in the timesheets.
No, they only provide a summary of the completed work, but not a
breakdown of the actual working intervals. However, you can use the
data in the timesheets to quickly adjust the bookings generated with
--freeze to match reality. But this is still a manual process as it
requires intelligent decisions from the project manager.
Chris
Is there a way to report with 'status' in bookings, like in a
timesheet?
No, status reporting has nothing to do with bookings. But you can use
journalentry to report status without using the timesheet syntax.
Chris
- Rene
Not directly. But setting the remaining 'effort' or 'duration' to 0
should tell the project manager to either close or completely remove
the task.
Chris