you have a number of options here. Yes, providing an end date for a
task switches to ALAP scheduling. But you can always override this
with following 'scheduling asap' attribute.
In your case, I'd recommend to use milestones for the deadlines and
make them depend on those task that you like to get finished by then.
By using the isdependencyof() function with hidetask you can create
nice reports that show exactly what tasks are targeting a certain
milestone.
Chris
R. A. Fisher
| From: | Chris Schlaeger <cschl...@gmail.com> |
| To: | taskjugg...@googlegroups.com |
| Date: | 11/17/2009 02:20 AM |
| Subject: | [taskjuggler-users] Re: Deadlines |
******************************************************************* IMPORTANT MESSAGE FOR RECIPIENTS IN THE U.S.A.: This message may constitute an advertisement of a BD group's products or services or a solicitation of interest in them. If this is such a message and you would like to opt out of receiving future advertisements or solicitations from this BD group, please forward this e-mail to optout...@bd.com. ******************************************************************* This message (which includes any attachments) is intended only for the designated recipient(s). It may contain confidential or proprietary information and may be subject to the attorney-client privilege or other confidentiality protections. If you are not a designated recipient, you may not review, use, copy or distribute this message. If you received this in error, please notify the sender by reply e-mail and delete this message. Thank you. ******************************************************************* Corporate Headquarters Mailing Address: BD (Becton, Dickinson and Company) 1 Becton Drive Franklin Lakes, NJ 07417 U.S.A. *******************************************************************