Hi Chris and all,
> taskjuggler.tjp:87: Error: Start date 2020-12-21-00:00-+0000 must be
> within the project time frame (2021-01-05-00:00-+0000 - 2021-05-25-00:00-+0000)
> booking t45962 2020-12-21 +4h
Hour bookings for example in pre-sales can happen before the official start of a project. Some resource may have contributed to an "early start". Or the official start of a project may have been delayed.
In all of these cases the actual delivered hours will be excluded from TaskJuggler reports, leading to incorrect results.
Is there a recommended way to work around this, without changing the start-
and end-dates of the project?
Cheers!
Frank