csv report: Is it possible to identify leaf/non-leaf tasks and milestone tasks ?

40 views
Skip to first unread message

vijay

unread,
Apr 7, 2022, 3:08:10 PM4/7/22
to TaskJuggler Users
I am trying to build some report generator on top of tj3, I understand the best parsable output from tj3 is the csv report.
I generated a report using all columns from https://taskjuggler.org/tj3/manual/columnid.html
I could not identify any column giving info on the task property (leaf/non leaf, milestone etc..)

Am I missing something?

Wolfram Wagner

unread,
Apr 9, 2022, 2:55:14 AM4/9/22
to taskjugg...@googlegroups.com
Beside a heuristic I have no idea. But you will have considered that
yet, right?
Children exist => container / no leaf
No Children, but effort or duration => leaf
No Children, neither effort nor duration => milestone