How to model a resource that is temporary part time available

29 views
Skip to first unread message

Nico van Haastrecht

unread,
Jul 7, 2025, 9:39:50 AMJul 7
to TaskJuggler Users
How to have a resource that is normally full time available but only for two months 1 day per week.

Thank for your reply,
Nico

Wolfram Wagner

unread,
Jul 7, 2025, 11:54:54 AMJul 7
to taskjugg...@googlegroups.com
You might assign him another dummy work with higher priority that
leaves him only that single day? Maybe?

best regards
Wolfram


Am Montag, dem 07.07.2025 um 05:37 -0700 schrieb 'Nico van Haastrecht'
via TaskJuggler Users:
> --
> You received this message because you are subscribed to the
> "TaskJuggler Users" group.
> To post to this group, send email to
> taskjugg...@googlegroups.com
> To unsubscribe from this group, send email to
> taskjuggler-us...@googlegroups.com
> For more information about TaskJuggler visit
> http://www.taskjuggler.org
> ---
> You received this message because you are subscribed to the Google
> Groups "TaskJuggler Users" group.
> To unsubscribe from this group and stop receiving emails from it,
> send an email to taskjuggler-us...@googlegroups.com.
> To view this discussion visit
> https://groups.google.com/d/msgid/taskjuggler-users/bb562621-bad6-4911-b121-2268287bafe1n%40googlegroups.com
> .

Erkan Özgür Yılmaz

unread,
Jul 8, 2025, 4:03:42 AMJul 8
to taskjugg...@googlegroups.com
You should be able to do it by defining a different working hours for that resource.

Erkan Ozgur Yilmaz


Reply all
Reply to author
Forward
0 new messages