use of mandatory with duration or length : bug or feature ?

1 view
Skip to first unread message

Mikael

unread,
Oct 29, 2010, 4:40:47 AM10/29/10
to TaskJuggler Development
Hello,

While using the mandatory attribute for tasks that require specific
resources to be present, I've noticed it only works as I expected when
combined with "effort" attribute.

But when combined with "duration" or "length", the mandatory resources
vacation are not taken into account.

I hoped to plan meetings by mixing mandatory and duration as that
seemed, but I have to use effort which seems a little less intuitive
in that case.

As I'm far from mastering tj, I just wonder if that's normal.

Regards,

Mikael

Grégoire Barbier

unread,
Oct 29, 2010, 4:25:27 PM10/29/10
to Mikael, taskjugg...@googlegroups.com, taskjug...@googlegroups.com
Hi Mikael,

I answer in the users mailing list rather than the dev one.

Le 29/10/2010 10:40, Mikael a �crit :

Can you confirm that you're using TJ2 and post a sample of your .tjp ?

--