Biggest power plant on the Earth

2 views
Skip to first unread message

Raman K

unread,
Sep 4, 2006, 3:35:22 AM9/4/06
to Vijayaraman
 

Biggest power plant on the Earth

ITAIPU- Largest power plant on the Earth- 12600 MW of Hydro power


 








Total view of the ITAIPU power plant
Left part shows overflow (spillway), the power station is located in the middle.


hyd_bus.jpg (30159 bytes)

At the bottom of the 196 m tall dam, the white tubes are containing the inlets for the 18 turbines (715 MW each).


hyd_on_damm.jpg (38566 bytes)

On top of the 7.6 km dam, a 12 800 000 m³ of concrete was used for the project ITAIPU.


hyd_lake.jpg (30263 bytes)

The lake created by ITAPU dam. Its area reaches 1 350 km2, its length 170 km and its average width 7 km.

One 715 MW electrical generator
The diameter of the rotor is almost 16 m, the rotating mass




hyd_in_damm.jpg (29696 bytes)


Inside the ITAIPU Powerhouse
Dimensions: length: 986 m, maximum height: 112 m and width: 99m.
The red line on the floor indicates the border of Brazil and Paraguay.


hyd_700MW.jpg (34112 bytes)

One 715 MW electrical generator
The diameter of the rotor is almost 16 m, the rotating mass is 2 650 t


hyd_control.jpg (32738 bytes)


The control center of the 18 generators
Left half of it (in Brazil) controls the 60 Hz units, right half  (in Paraguay) controls the 50 Hz units.


hyd_AC_trans.JPG (47323 bytes)

A 18 kV to 525 kV transformator for 825 MVA
To increase the voltage To increase the voltage of the  generators, transformers with a capacity of 825 MVA and 768 MV(for 50 and 60 Hz respectively) were specified.


hyd_high_voltage.jpg (53413 bytes)

Power switches for high voltages
Power switches at the "Left Bank Substation" (FURNAS).


hyd_dc_ac.jpg (39632 bytes)

The AC-DC rectifier
The FURNAS rectifier substation is accomplished by four lines of of 500 kV.
Output DC voltages are symmetrical ± 500 000 Volt SC.


hyd_last.jpg (30166 bytes)

Electricity (AC) leaving ITAPU to Sao Paulo
6 300 MW of electrical power generated by the 60 Hz units is transported by an 891 km AC transmission system, formed by three lines of 750 kV.



"Peanuts"- a word often used from so called "economic experts" and representatives when it comes to Renewable Energies.
"Not sufficient", "unreliable", "not feasible", are common bias.


ITAIPU shows they are wrong! Having more power than 10 nuclear power stations it supplies the second largest city on the planet with zero-emission electricity since 1984, still being extended until 1991. 26% of the electrical power consumption of Brazil and 78% of Paraguay are supplied by ITAIPU.

Located at the Brazilian-Paraguaian border and not far from the Argentinian border, the first step of the initiation was already in 1966 when the Ministers of Foreign Affairs of Brazil and Paraguay signed a joint statement known as the "Act of Ygazu". By this a study and evaluation of the hydraulic resources of the Parana river (owned jointly by Brazil and Paraguay) followed.

On April, 26, 1973, the two governments of the states signed a treaty "for the development of the hydroelectric resources of the Parana River" and founded "ITAIPU Binacional" (cooperation with the legal, administrative and financial capacities and technical responsibility to plan, set up and operate the plant) in May, 17, 1974.

The construction work started in 1975, reaching its peak in 1978 with 30 000 people at work. Monthly on-site concrete production reached 338 000 m³. In total, 15 times the mass of concrete used for the "Eurotunnel" was supplied. The height of the dam reaches 196 m, its length 7.76 km. The lake created by this is 170 km long and contains 29 billion tons of water.


Unit 1 started to operate in December 1983. Electrical grid connection to Paraguay was established in March 1984, Brazil was connected 5 months later. In March 1991 the last unit (No.18) was put into operation.

The water intake of one single 715 MW Francis-turbine is 700 m³/s, its weighted efficiency is 93.8%.

Each year ITAPU generates 75 TWh of electricity and avoids 67.5 million tons of carbon dioxide emissions - compared to coal power plants.
The final cost of ITAIPU amounts to US$ 20 billion, 50% of this value are direct investments and balance financial charges.

If whole area of the lake - at nominal level - would be covered by solar modules the power of the would be 135 000 MWp, which would produce 230 TWh a year. For the same yearly output as ITAIPU a solar PV-plant would cost US$ 132 billion


Technical Data

Powerhouse and Main Dam
Location of the Equipment and Principal Elevations

 

 

Powerhouse (18 units including erection bays) - (m)

Length

968

Width

99

Height

112

Roof level

148

Generator hall floor level

108

Spacing between units

34



 
 

 

01 - El 40

- Foundation of the dam

02 - El 92,4

- Access to turbine pit

03 - El 98,5

- Unit auxiliary service - Pure water system

04 - El 98,5

- Excitation system, access to generator housing and speed governo

05 - El 108

- Step-up transformers

06 - El 108

- Generator hall floor and local control rooms

07 - El 122

- Ventilation system

08 - El 127,6

- Cable gallery

09 - El 128,2

- GIS - SF6

10 - El 133,2

- Principal panels of AC auxiliary service and diesel generator hall

11 - El 144

- Dam auxiliary service

12 - El 214

- Gate hydraulic pump group



 





 

 

Rolling track of gantry crane

Rolling track (m)

 

Span

10,00

Total length

857,6

Rail-top elevation

225



 
 

 

Penstocks

Quantity

18

Weight each penstock (t)

883

Internal diameter (m)

10,5

Developed length (m)

142,2

Rated flow (m³ / s)

690



 
 

 

Water Intake Trashracks

Quantity

18

Rack panels per intake

24 (m) 4,7 x 5,5



 
 

 

Trashrack Cleaning Machine

Quantity

2

Jib crane capacity (kN)

200

Vertical lift of rake (m)

61,5

Rake capacity (m³ / kN)

2/2,5



 
 

 

Service Gates (Fixed wheel type)

Quantity

18

Span (m)

8,2

Total height (m)

19,3

Sill beam elevation (m)

177,6

Maximum flow through gate (m³/s)

750



 
 

 

Stop-logs

Sill beam elevation (m)

177,2

Span (m)

7,5

Height (m)

17,5

Quantity

7



 
 

 

Gantry cranes

Quantity

2

Capacity (kN)

1.100/400

Max. hoisting speed 50/60 Hz (m/min.)

4,6/5,5

Min. hoisting speed 50/60 Hz (m/min.)

1,7/2,0

Rated travel speed 50/60 Hz (m/min.)

25/30



 





 

 

Generator

Quantity

18

Frequency

60 Hz (9 un.) / 50 Hz (9 un.)

Rated power

50 / 60 Hz (MVA) 823,6 / 737,0

Rated voltage (kV)

18

Number of poles

50 / 60 Hz 66 / 78

Moment of inertia - GD2 (t.m²)

320.000

Power factor

50 / 60 Hz 0,85 / 0,95

Heaviest component - rotor (t)

1.760

Weight of each unit 50 / 60 Hz (t)

3.343 / 3.242



 






 

 

Turbine

Quantity

18

Type

Francis

Rated power (MW)

715

Design speed - 50 / 60 Hz (rpm)

90,9 /92,3

Net design head (m)

118,4

Rated flow (m³/s)

645

Heaviest component - rotor (t)

296

Weight of each unit (t)

3.360



 


 

 

Bank of Single-Phase Transformers

50 Hz 9 + 2 Reserve Units

60 Hz 9 + 2 Reserve Units

 

Rated Power of Each Bank

50 / 60 Hz (MVA) 825/768

 

Impulse Level (Phase/Neutral)

High Voltage (kV) 1.550/110

Low Voltage (kV) 125

Type of connection - Y

 

Weight of each transformer (kg)

217 x 103 (50 Hz)

189 x 103 (60 Hz)

Cooling forced oil and water



 
 

 

SF6 Gas Insulated Substation

Maximum Rated Voltage (kV)

550

Rated Current (A)

4.000

Rated Break Current (kA)

63

Quantity of Circuit Breakers

52

Length of Enclosed Busbars Isolated by SF6 Gas (m)

7.500

SF6 Pressure in the Circuit Breakers (kPa)

620

Quantity of Isolation Switches

124

Quantity of Current Transformers

396

Quantity of Potential Transformers

24

Quantity of Surge Arresters

126

Mass of SF6 Gas (kg)

108 x 103



 


S
CADA - Supervisory Control and Data Acquisition

The SCADA System, is a means of supervision and control based on computers. The general purpose of this System is to provide the Plant Operators with detailed and automatic information in a centralized form - at present being distributed over more that 1,500 panels in the diverse galleries along the length of the power plant - and organized in real time (that is, at the instant of occurrence) concerning the electrical, mechanical, thermal and hydraulic conditions of the equipment and the installations. This will permit the operators in the Central Control Room to exercise a permanent analysis of the situation and facilitate taking the correct and appropriate decisions within the time limits necessary to maintain the generation of energy.

Its operation is based on the installation of electronic devices in the diverse units of equipment in the Power Plant (generators, turbines, transformers, etc.) for the automatic acquisition of operational information. This information will be transferred to a central computer, where it will be processed by specific software. When the software identifies abnormal conditions, the Operators will be instantly informed by signals on the computer monitors. The required corrective actions or commands can be taken through these same computers.

The SCADA System is scheduled to be installed by the middle of 2002 and will provide the Operators with supervision over approximately 18,000 points, significantly improving the operating conditions of the Plant and permitting, in many cases, the prevention of disconnections, as well as allowing greater speed of recovery from the operational problems that may occur.







Transmission system

 

 


 






--
K.Raman.

bharani jude

unread,
Sep 8, 2006, 6:34:41 AM9/8/06
to ani....@rediffmail.com, meena senthil, smro...@ucdavis.edu, athis...@yahoo.co.in, Catherine Wedderburn, tamilco...@googlegroups.com, hearts_...@yahoo.co.in, keswa...@yahoo.co.in, kutty...@hotmail.com


---------- Forwarded message ----------
From: Raman K <kram...@gmail.com>
Date: Sep 4, 2006 1:05 PM
Subject: [Tamil] Biggest power plant on the Earth
To: Vijayaraman <vija...@gmail.com>

Biggest power plant on the Earth

ITAIPU- Largest power plant on the Earth- 12600 MW of Hydro power


 








Total view of the IT AIPU power plant


Left part shows overflow (spillway), the power station is located in the middle.


hyd_bus.jpg (30159 bytes)

At the bottom of the 196 m tall dam, the white tubes are containing the inlets for the 18 turbines (715 MW each).


hyd_on_damm.jpg (38566 bytes)

On top of the 7.6 km dam, a 12 800 000 m³ of concrete was used for the project ITAIPU.


hyd_lake.jpg (30263 bytes)



The lake created by ITAPU dam. Its area reaches 1 350 km 2, its length 170 km and its average width 7 km.



Unit 1 started to operate in December 1983. Electrical grid connection to Paraguay was established in March 1984, Brazil was connected 5 months later. In March 1991 the last unit ( No.18) was put into operation.


The water intake of one single 715 MW Francis-turbine is 700 m³/s, its weighted efficiency is 93.8%.

Each year ITAPU generates 75 TWh of electricity and avoids 67.5 million tons of carbon dioxide emissions - compared to coal power plants.
The final cost of ITAIPU amounts to US$ 20 billion, 50% of this value are direct investments and balance financial charges.

If whole area of the lake - at nominal level - would be covered by solar modules the power of the would be 135 000 MW p, which would produce 230 TWh a year. For the same yearly output as ITAIPU a solar PV-plant would cost US$ 132 billion

Technical Data


 






--
K.Raman.
Reply all
Reply to author
Forward
0 new messages