Greetings everyone,
On March 14, the Transportation Action Team hosted a public forum on the Corvallis Pavement Rehabilitation Program. About 40 people attended the online event and over 65 people have viewed the recording. Public Works staff addressed many of the questions and concerns submitted by residents during the forum but didn't have time to get to all of them. Also, the comment period remained open for a week after the event. Attached to this email is the response by Public Works staff to the remaining questions and comments.
Please remember that this inaugural public forum was scheduled after this specific project on NE Circle Boulevard was scoped, budgeted, and designed. Public Works stated that future events would be held closer to the beginning of the planning process for a project, which would allow for greater public input on its design.